Question 92

Analyzing the strengths, weaknesses, opportunities, and threats (SWOT) of a project is known as:

Options:

A.

calculating cost of quality

B.

comparing project benefits

C.

performing measurements analysis

D.

identifying risks

Discussion
Alaia
These Dumps are amazing! I used them to study for my recent exam and I passed with flying colors. The information in the dumps is so valid and up-to-date. Thanks a lot!!!
Zofia Sep 9, 2024
That's great to hear! I've been struggling to find good study material for my exam. I will ty it for sure.
Ari
Can anyone explain what are these exam dumps and how are they?
Ocean Oct 16, 2024
They're exam preparation materials that are designed to help you prepare for various certification exams. They provide you with up-to-date and accurate information to help you pass your exams.
Esmae
I highly recommend Cramkey Dumps to anyone preparing for the certification exam.
Mollie Aug 15, 2024
Absolutely. They really make it easier to study and retain all the important information. I'm so glad I found Cramkey Dumps.
Melody
My experience with Cramkey was great! I was surprised to see that many of the questions in my exam appeared in the Cramkey dumps.
Colby Aug 17, 2024
Yes, In fact, I got a score of above 85%. And I attribute a lot of my success to Cramkey's dumps.
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Sep 26, 2024
Thanks for the recommendation! I'll check it out.
Question 93

The CPI is .92, and the EV is US$172,500. What is the actual cost of the project?

Options:

A.

US$158,700

B.

US$172,500

C.

US$187,500

D.

US$245,600

Discussion
Question 94

Which input may influence quality assurance work and should be monitored within the context of a system for configuration management?

Options:

A.

Work performance data

B.

Project documents

C.

Scope baseline

D.

Requirements documentation

Discussion
Question 95

The chart below is an example of a:

Questions 95

Options:

A.

Responsibility assignment matrix (RAM)

B.

Work breakdown structure (WBS)

C.

RACI chart

D.

Requirements traceability matrix

Discussion
Page: 23 / 34