Question 92

Analyzing the strengths, weaknesses, opportunities, and threats (SWOT) of a project is known as:

Options:

A.

calculating cost of quality

B.

comparing project benefits

C.

performing measurements analysis

D.

identifying risks

Discussion
Aliza
I used these dumps for my recent certification exam and I can say with certainty that they're absolutely valid dumps. The questions were very similar to what came up in the actual exam.
Jakub Jul 29, 2025
That's great to hear. I am going to try them soon.
Victoria
Hey, guess what? I passed the certification exam! I couldn't have done it without Cramkey Dumps.
Isabel Jul 10, 2025
Same here! I was so surprised when I saw that almost all the questions on the exam were exactly what I found in their study materials.
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Jul 9, 2025
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Alaya
Best Dumps among other dumps providers. I like it so much because of their authenticity.
Kaiden Jul 23, 2025
That's great. I've used other dump providers in the past and they were often outdated or had incorrect information. This time I will try it.
Kingsley
Do anyone guide my how these dumps would be helpful for new students like me?
Haris Jul 5, 2025
Absolutely! They are highly recommended for anyone looking to pass their certification exam. The dumps are easy to understand and follow, making it easier for you to study and retain the information.
Question 93

The CPI is .92, and the EV is US$172,500. What is the actual cost of the project?

Options:

A.

US$158,700

B.

US$172,500

C.

US$187,500

D.

US$245,600

Discussion
Question 94

Which input may influence quality assurance work and should be monitored within the context of a system for configuration management?

Options:

A.

Work performance data

B.

Project documents

C.

Scope baseline

D.

Requirements documentation

Discussion
Question 95

The chart below is an example of a:

Questions 95

Options:

A.

Responsibility assignment matrix (RAM)

B.

Work breakdown structure (WBS)

C.

RACI chart

D.

Requirements traceability matrix

Discussion