Question 128

What scope definition technique is used to generate different approaches to execute and perform the work of the project?

Options:

A.

Build vs. buy

B.

Expert judgment

C.

Alternatives identification

D.

Product analysis

Discussion
Miriam
Highly recommended Dumps. 100% authentic and reliable. Passed my exam with wonderful score.
Milan Nov 10, 2025
I see. Thanks for the information. I'll definitely keep Cramkey in mind for my next exam.
Miley
Hey, I tried Cramkey Dumps for my IT certification exam. They are really awesome and helped me pass my exam with wonderful score.
Megan Nov 10, 2025
That’s great!!! I’ll definitely give it a try. Thanks!!!
Billy
It was like deja vu! I was confident going into the exam because I had already seen those questions before.
Vincent Nov 16, 2025
Definitely. And the best part is, I passed! I feel like all that hard work and preparation paid off. Cramkey is the best resource for all students!!!
Alaya
Best Dumps among other dumps providers. I like it so much because of their authenticity.
Kaiden Nov 1, 2025
That's great. I've used other dump providers in the past and they were often outdated or had incorrect information. This time I will try it.
Cecilia
Yes, I passed my certification exam using Cramkey Dumps.
Helena Nov 10, 2025
Great. Yes they are really effective
Question 129

Which tool or technique is effective in a project in which the deliverable is not a service or result?

Options:

A.

Inspection

B.

Variance analysis

C.

Decomposition

D.

Product analysis

Discussion
Question 130

The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:

Options:

A.

start-to-start (SS)

B.

start-to-finish (SF)

C.

finish-to-start (FS)

D.

finish-to-finish (FF)

Discussion
Question 131

The PV is $1000, EV is $2000, and AC is $1500. What is CPI?

Options:

A.

1.33

B.

2

C.

0.75

D.

0.5

Discussion