Question 20

Enterprise environmental factors are an input to which process?

Options:

A.

Control Scope

B.

Define Scope

C.

Plan Scope Management

D.

Collect Requirements

Discussion
Peyton
Hey guys. Guess what? I passed my exam. Thanks a lot Cramkey, your provided information was relevant and reliable.
Coby Dec 1, 2025
Thanks for sharing your experience. I think I'll give Cramkey a try for my next exam.
Honey
I highly recommend it. They made a big difference for me and I'm sure they'll help you too. Just make sure to use them wisely and not solely rely on them. They should be used as a supplement to your regular studies.
Antoni Dec 10, 2025
Good point. Thanks for the advice. I'll definitely keep that in mind.
Ernest
That's amazing. I think I'm going to give Cramkey Dumps a try for my next exam. Thanks for telling me about them! CramKey admin please share more questions……You guys are amazing.
Nate Dec 19, 2025
I failed last week, I never know this site , but amazed to see all these questions were in my exam week before. I feel bad now, why I didn’t bother this site. Thanks Cramkey, Excellent Job.
Wyatt
Passed my exam… Thank you so much for your excellent Exam Dumps.
Arjun Dec 21, 2025
That sounds really useful. I'll definitely check it out.
Question 21

Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?

Options:

A.

Decomposition

B.

Inspection

C.

Project analysis

D.

Document analysis

Discussion
Question 22

The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:

Options:

A.

Plan Schedule Management.

B.

Develop Project Charter.

C.

Develop Schedule.

D.

Plan Scope Management.

Discussion
Question 23

Organizations manage portfolios based on which of the following types of plans?

Options:

A.

Strategic

B.

Project

C.

Program

D.

Operational

Discussion
Page: 5 / 34
Title
Questions
Posted

PMI-001
PDF

$26.25  $104.99

PMI-001 Testing Engine

$31.25  $124.99

PMI-001 PDF + Testing Engine

$41.25  $164.99