Question 100

Using the following data, what is the Schedule Performance Index (SPI)?

EV= $500 PV= $750 AC= $1000 BAC= $1200

Options:

A.

0.67

B.

1.5

C.

0.75

D.

0.5

Discussion
Miley
Hey, I tried Cramkey Dumps for my IT certification exam. They are really awesome and helped me pass my exam with wonderful score.
Megan Sep 4, 2025
That’s great!!! I’ll definitely give it a try. Thanks!!!
Laila
They're such a great resource for anyone who wants to improve their exam results. I used these dumps and passed my exam!! Happy customer, always prefer. Yes, same questions as above I know you guys are perfect.
Keira Sep 3, 2025
100% right….And they're so affordable too. It's amazing how much value you get for the price.
Lennie
I passed my exam and achieved wonderful score, I highly recommend it.
Emelia Sep 14, 2025
I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Anaya
I found so many of the same questions on the real exam that I had already seen in the Cramkey Dumps. Thank you so much for making exam so easy for me. I passed it successfully!!!
Nina Sep 9, 2025
It's true! I felt so much more confident going into the exam because I had already seen and understood the questions.
Question 101

Which items are an output of the Perform Integrated Change Control process?

Options:

A.

Work performance reports

B.

Accepted deliverables

C.

Project management plan updates

D.

Organizational process assets

Discussion
Question 102

When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:

Options:

A.

event.

B.

response,

C.

perception.

D.

impact.

Discussion
Question 103

What is the name of the statistical method that helps identify which factors may influence specific variables of a product or process under development or in production?

Options:

A.

Failure modes and effects analysis

B.

Design of experiments

C.

Quality checklist

D.

Risk analysis

Discussion