PMI Updated PMI-001 Exam Questions and Answers by lexie

Page: 33 / 34

PMI PMI-001 Exam Overview :

Exam Name: Project Management Professional v5
Exam Code: PMI-001 Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 918 Q&A's Shared By: lexie
Question 132

Which of the following change requests can bring expected future performance of the project work in line with the project management plan?

Options:

A.

Corrective action

B.

Defect repair

C.

Preventative action

D.

Probable action

Discussion
Stefan
Thank you so much Cramkey I passed my exam today due to your highly up to date dumps.
Ocean Sep 7, 2025
Agree….Cramkey Dumps are constantly updated based on changes in the exams. They also have a team of experts who regularly review the materials to ensure their accuracy and relevance. This way, you can be sure you're studying the most up-to-date information available.
Josephine
I want to ask about their study material and Customer support? Can anybody guide me?
Zayd Sep 27, 2025
Yes, the dumps or study material provided by them are authentic and up to date. They have a dedicated team to assist students and make sure they have a positive experience.
Faye
Yayyyy. I passed my exam. I think all students give these dumps a try.
Emmeline Sep 15, 2025
Definitely! I have no doubt new students will find them to be just as helpful as I did.
Aryan
Absolutely rocked! They are an excellent investment for anyone who wants to pass the exam on the first try. They save you time and effort by providing a comprehensive overview of the exam content, and they give you a competitive edge by giving you access to the latest information. So, I definitely recommend them to new students.
Jessie Aug 31, 2025
did you use PDF or Engine? Which one is most useful?
Question 133

An input to Conduct Procurements is:

Options:

A.

Independent estimates.

B.

Selected sellers.

C.

Seller proposals.

D.

Resource calendars.

Discussion
Question 134

Outputs from constituent processes might be used as:

Options:

A.

Inputs to other processes.

B.

Proof of process completion.

C.

Identification of project tasks.

D.

Indicators to eliminate project redundancies.

Discussion
Question 135

What are assigned risk ratings based upon?

Options:

A.

Root cause analysis

B.

Assessed probability and impact

C.

Expert judgment

D.

Risk Identification

Discussion