Spring Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

FIDIC Updated CCM Exam Questions and Answers by madiha

Page: 3 / 10

FIDIC CCM Exam Overview :

Exam Name: Certified Contract Manager
Exam Code: CCM Dumps
Vendor: FIDIC Certification: Contract Manager
Questions: 140 Q&A's Shared By: madiha
Question 12

(In a region experiencing civil unrest and armed conflict under a FIDIC Red Book 1999 Contract, violence escalates into an insurrection, forcing the Contractor to stop work and retreat to a secured compound. The Contractor issues a notice claiming this is an Employer’s Risk under Sub-Clause 17.3 (a) and (b), requesting Extension of Time and Cost. What is the most appropriate position for the Engineer at this stage?)

Options:

A.

This is an Employer’s Risk under Sub-Clause 17.3 (a)/(b), and the Contractor is entitled to EOT and Cost. The Engineer will assess actual entitlement after the event; no further notices are required.

B.

Violence is an Employer’s Risk; however, the Contractor can only claim after the situation ends. The Engineer cannot determine EOT or Cost yet, and the Contractor must submit a fully detailed claim later.

C.

The Contractor should have foreseen such risks due to the region’s history; therefore, Clause 19 is not applicable.

D.

The Employer is in breach of its obligation to provide safe working conditions under Sub-Clause 2.1; therefore, the Contractor can claim on that basis.

Discussion
Question 13

Which two of the following statements are correct regarding the dayworks under FIDIC Red, Yellow, and Silver Books (both editions)?

Choose all of the correct answers (multiple possibilities).

Options:

A.

If a Daywork Schedule is not included in the Contract, the Sub-Clause related to dayworks shall not apply.

B.

The dayworks related Sub-Clause is also applicable to other types of works.

C.

The dayworks related Sub-Clause is only used for remeasurement in the FIDIC Red Book (both editions) only.

D.

The Engineer (or the Employer in case of FIDIC Silver Book) may instruct that " a Variation shall " be executed on a daywork basis.

Discussion
Question 14

(Which two FIDIC Books (edition 2017) should especially be considered for use if the Employer needs the Contractor to take responsibility for the design and execution of the project. The construction will involve substantial work underground or work in other areas which tenderers cannot inspect.

Choose all of the correct answers (multiple possibilities).)

Options:

A.

Yellow Book

B.

Red Book

C.

Silver Book by amending Sub-Clause 4.12 in the Particular Conditions

D.

Silver Book without amending Sub-Clause 4.12 in the Particular Conditions

Discussion
Nell
Are these dumps reliable?
Ernie Mar 9, 2026
Yes, very much so. Cramkey Dumps are created by experienced and certified professionals who have gone through the exams themselves. They understand the importance of providing accurate and relevant information to help you succeed.
Ella-Rose
Amazing website with excellent Dumps. I passed my exam and secured excellent marks!!!
Alisha Mar 24, 2026
Extremely accurate. They constantly update their materials with the latest exam questions and answers, so you can be confident that what you're studying is up-to-date.
Ivan
I tried these dumps for my recent certification exam and I found it pretty helpful.
Elis Mar 14, 2026
Agree!!! The questions in the dumps were quite similar to what came up in the actual exam. It gave me a good idea of the types of questions to expect and helped me revise efficiently.
Ernest
That's amazing. I think I'm going to give Cramkey Dumps a try for my next exam. Thanks for telling me about them! CramKey admin please share more questions……You guys are amazing.
Nate Mar 8, 2026
I failed last week, I never know this site , but amazed to see all these questions were in my exam week before. I feel bad now, why I didn’t bother this site. Thanks Cramkey, Excellent Job.
Question 15

The Employer has prepared a contract for a waste-to-energy project based on the FIDIC Yellow Book (edition 1999). You are preparing negotiations on behalf of one of the Subcontractors with the Contractor. The main Contractor will manage the design and build of the Works, whereby the Subcontractor will deliver critical systems regarding power generation and cooling. The Contractor intends to contract the main Contract back-to-back with the Subcontractor. In the proposed back-to-back subcontract, the following amendment is proposed through Particular Conditions:

" Sub-Clause 4.4. The following paragraph is added: The Subcontractor is required to scrutinize the Employer ' s Requirements in a manner identical to the obligations of the Contractor as stated in Sub-Clause 5.1 of the Main Contract. The Subcontractor will indemnify and hold harmless (up to the maximum liability of the Subcontractor) the Contractor with regard to any error, fault or other defect found in the Employer ' s Requirements, its items of reference or Contractor ' s design of the Works for the scope part for which Subcontractor is contracted. "

What is your advice to the Subcontractor (SC) in regard to entering this proposed subcontract?

Options:

A.

I would advise the SC to enter the Contract with the request to the Contractor to delete this amendment in the Particular Conditions. If the Contractor does not agree to do so, at least the Subcontractor has tried its best.

B.

I would advise the SC not to enter this contract because the Contractor is obliged to act in accordance with good faith. A proposed paragraph like this opposes good faith.

C.

I would advise the SC not to enter this contract, because Sub-Clause 4.4 describes the obligations of SC towards Contractor, but this amendment positions the SC in a vulnerable position for claims regarding all errors, faults or other Defects (whether originating from the Employer ' s Requirements or the design of the Contractor). Essentially, this means the SC becomes liable for the design part, which is within the scope of Contractor even

D.

I would advise the SC to discuss this amendment with the insurance company just to be sure there will be no transfer of risks. This amendment is mainly a consequence of the FIDIC Yellow Book structure, where the Contractor has obligations in terms of scrutinizing the Employer ' s Requirements. This amendment makes this obligation more explicit. If the insurance company has no problems with insuring the parts which will be delivered by SC to

Discussion
Page: 3 / 10

CCM
PDF

$36.75  $104.99

CCM Testing Engine

$43.75  $124.99

CCM PDF + Testing Engine

$57.75  $164.99