Question 24

(Which of the following two statements are correct regarding subcontractors under FIDIC Red, Yellow, and Silver Books (edition 2017)?

Choose all of the correct answers (multiple possibilities).)

Options:

A.

The Contractor shall obtain the Engineer’s and the Employer’s prior consent to all Subcontractors.

B.

If no maximum allowable accumulated value of work subcontracted is stated in the Contract Data, the Contractor shall not be entitled to subcontract the whole of the Works without prior consent of the Engineer.

C.

The Contractor shall not be responsible for the acts or defaults of any Subcontractor.

D.

The Contract Data may identify parts of the Works which the Contractor is not entitled to subcontract.

Discussion
Norah
Cramkey is highly recommended.
Zayan Oct 22, 2026
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Miriam
Highly recommended Dumps. 100% authentic and reliable. Passed my exam with wonderful score.
Milan Oct 22, 2026
I see. Thanks for the information. I'll definitely keep Cramkey in mind for my next exam.
Kingsley
Do anyone guide my how these dumps would be helpful for new students like me?
Haris Oct 9, 2026
Absolutely! They are highly recommended for anyone looking to pass their certification exam. The dumps are easy to understand and follow, making it easier for you to study and retain the information.
Cecilia
Yes, I passed my certification exam using Cramkey Dumps.
Helena Oct 6, 2026
Great. Yes they are really effective
Ernest
That's amazing. I think I'm going to give Cramkey Dumps a try for my next exam. Thanks for telling me about them! CramKey admin please share more questions……You guys are amazing.
Nate Oct 12, 2026
I failed last week, I never know this site , but amazed to see all these questions were in my exam week before. I feel bad now, why I didn’t bother this site. Thanks Cramkey, Excellent Job.
Question 25

Which one of the following documents constitutes a contract and is considered binding on both parties, when the Employer wants to award the Contract to the tenderer?

Options:

A.

Letter of Acceptance

B.

Letter of Intent

C.

Memorandum of understanding

D.

Letter of Intent & Memorandum of understanding

Discussion
Question 26

FIDIC Red, Yellow, and Silver Books (both editions) contain a provision for the Engineer or Employer to instruct the Contractor to employ a subcontractor, thereby also permitting the Contractor to refuse to employ such proposed subcontractor on the basis of a reasonable objection by a notice. Is this statement true or false?

Options:

A.

True

B.

False

Discussion
Question 27

Under the FIDIC Construction Contract, which one of the following statements is correct?

Options:

A.

Payments of a DAB Member ' s retainer fee is the sole responsibility of the Contractor.

B.

For an ad-hoc DAB, a retainer fee for each DAB Member must be paid to the Member on the first day of each calendar month.

C.

Payment to DAB Members must be certified by the Employer.

D.

If all persons nominated to serve as members of an ad hoc DAB do not sign a DAB Agreement, an appointing entity can make appointments.

E.

A DAB must give its decision in writing on any dispute when requested by one of the Parties.