Question 28

You are the Contract Manager in a highway project using FIDIC Red Book (edition 1999). You work for the Employer – a highway management agency. During the tender period, you are informed of a specific Commencement Date required by the directors of the agency. Which two of the following approaches to inform the tenderers of this date are clearly and unambiguously drafted?

Choose all of the correct answers (multiple possibilities).

Options:

A.

Specify Commencement Date in the Minutes of Meeting of Contract Negotiation.

B.

Specify Commencement Date in the Contract Agreement.

C.

Specify Commencement Date in the Particular Conditions.

D.

Inform the Commencement Date to the tenderers by email, and attach that email in the list of Contract Documents.

Discussion
Question 29

You are the new Contract Manager of the Contractor in a bridge project using FIDIC Yellow Book (edition 2017). The project had been suspended due to a material change in the Employer ' s financial arrangement. You have worked with your team to identify several failures of the Employer in carrying its obligations under the Contract. Which one of the following does NOT allow the Contractor to issue Notice to terminate the Contract?

Options:

A.

A prolonged suspension for more than 1 year has affected the whole of the Works.

B.

The Contractor does not receive the amount due under the latest Payment Certificate for more than 4 months after the due date.

C.

The Contractor has requested the Employer but has not received any evidence that the financial arrangement is being maintained, despite having sent a notice thereto 4 months earlier.

D.

The Employer failed to comply with a final and binding determination issued by the Engineer, and such failure constitutes a material breach of the Employer ' s obligations under the Contract.

Discussion
Question 30

What are two differences between a notice and other communications under the FIDIC Red Book (edition 2017)? (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

Notice is a defined term, while other communications are not defined as a term in the General Conditions.

B.

Contractually there is no difference between a notice and other communications.

C.

Both ' Notice ' and ' Other Communications ' are defined terms under the Conditions of Contract.

D.

The Parties and Engineer shall be given original or copy of any Notice, Notice of Dissatisfaction (NOD) and Certificates, which is not always the case for other communications.

Discussion
Honey
I highly recommend it. They made a big difference for me and I'm sure they'll help you too. Just make sure to use them wisely and not solely rely on them. They should be used as a supplement to your regular studies.
Antoni Jun 22, 2026
Good point. Thanks for the advice. I'll definitely keep that in mind.
Miley
Hey, I tried Cramkey Dumps for my IT certification exam. They are really awesome and helped me pass my exam with wonderful score.
Megan Jun 26, 2026
That’s great!!! I’ll definitely give it a try. Thanks!!!
Stefan
Thank you so much Cramkey I passed my exam today due to your highly up to date dumps.
Ocean Jun 20, 2026
Agree….Cramkey Dumps are constantly updated based on changes in the exams. They also have a team of experts who regularly review the materials to ensure their accuracy and relevance. This way, you can be sure you're studying the most up-to-date information available.
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson Jun 12, 2026
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Question 31

Before applying the procurement process of any FIDIC Book, the Employer should always check if there are local procurement rules that also apply. Which one of these responses is correct?

Options:

A.

No, because the FIDIC procurement process is universal.

B.

No, because Employers never have specific procurement rules.

C.

Yes, based on the law system, internal governance or type of Employer additional procurement rules can apply.

D.

Yes, but this is only applicable for public entities like governments. If the Employer is a private organisation (like a company), they are free to procure how they want.

Discussion
Page: 7 / 10

CCM
PDF

$36.75  $104.99

CCM Testing Engine

$43.75  $124.99

CCM PDF + Testing Engine

$57.75  $164.99