Spring Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

FIDIC Updated CCM Exam Questions and Answers by jennifer

Page: 8 / 10

FIDIC CCM Exam Overview :

Exam Name: Certified Contract Manager
Exam Code: CCM Dumps
Vendor: FIDIC Certification: Contract Manager
Questions: 140 Q&A's Shared By: jennifer
Question 32

Upon review of the revised programme, submitted by the Contractor, if the Engineer (under FIDIC Red or Yellow Books) or Employer (under FIDIC Silver Book) does not give a Notice of Non-Compliance within 14 days after receiving a revised programme, then ... [complete the sentence, thereby considering FIDIC Red, Yellow, and Silver Books (edition 2017)]. (1 correct answer applies)

Options:

A.

The Contractor shall submit a Notice to the Engineer or the Employer reminding him to give its approval on the revised programme.

B.

The Engineer shall be deemed to have given a Consent and the revised programme shall be the Programme.

C.

The Contractor cannot proceed in accordance with the Programme.

D.

The Engineer is deemed to have no objection to use the revised programme submitted by the Contractor, for the Works.

Discussion
Madeleine
Passed my exam with my dream score…. Guys do give these dumps a try. They are authentic.
Ziggy Mar 24, 2026
That's really impressive. I think I might give Cramkey Dumps a try for my next certification exam.
Miley
Hey, I tried Cramkey Dumps for my IT certification exam. They are really awesome and helped me pass my exam with wonderful score.
Megan Mar 4, 2026
That’s great!!! I’ll definitely give it a try. Thanks!!!
Ayesha
They are study materials that are designed to help students prepare for exams and certification tests. They are basically a collection of questions and answers that are likely to appear on the test.
Ayden Mar 4, 2026
That sounds interesting. Why are they useful? Planning this week, hopefully help me. Can you give me PDF if you have ?
Ilyas
Definitely. I felt much more confident and prepared because of the Cramkey Dumps. I was able to answer most of the questions with ease and I think that helped me to score well on the exam.
Saoirse Mar 15, 2026
That's amazing. I'm glad you found something that worked for you. Maybe I should try them out for my next exam.
Question 33

When is the Employer obliged to return the Performance Security (PS) under the FIDIC Red Book (edition 1999)?

Options:

A.

Without undue delay after the issuance of the Taking-Over Certificate.

B.

Without undue delay after the issuance of the Performance Certificate.

C.

Within 21 days after the issuance of the Taking-Over Certificate.

D.

Within 21 days after the issuance of the Performance Certificate.

Discussion
Question 34

A Contractor under the FIDIC Silver Book (edition 1999) has not been able to finish the Works within the Time for Completion as mentioned in the Contract and has overrun the Time for Completion by 3 months. This results in a significant claim of $4,500,000 from the Employer. The Employer has submitted this claim to the Contractor according to the procedures as mentioned in the Contract. The Contractor asks you for advice and refers to Clause 8. Which one of the following statements is NOT true?

Options:

A.

If there are Variations agreed between the Contractor and the Employer, the Contractor should check if an adjustment for Time for Completion was part of any of these Variations.

B.

The root cause of the delay has to be determined by the Contractor, thereby especially verifying if the cause of the delay lies in a delay caused by the Authorities.

C.

In addition to the delay damages as mentioned in Sub-Clause 2.5, the Employer has the right to claim any extra costs it has to make due to the delay, as delay damages are not seen as compensation for costs incurred by the Employer, but only as an incentive for the Contractor to perform on time.

D.

If the delay is entirely caused by the Employer having instructed the Contractor to suspend progress during the Works, while the cause of the suspension is not the responsibility of the Contractor, the claim for delay damages was wrongfully issued.

Discussion
Question 35

(Which two of the following statements are correct regarding types of Claims under the FIDIC Red, Yellow, and Silver Books (edition 2017)?

Choose all of the correct answers (multiple possibilities).)

Options:

A.

The limit in time referred to in Sub-Clause 20.2.1 (also known as time bar) applies to all types of Claims.

B.

If a Claim is submitted as per sub-paragraph (c) of Sub-Clause 20.1, this is dealt with by the Engineer or Employer’s Representative (in case of FIDIC Silver Book) as per Sub-Clause 3.7/3.5.

C.

If a Claim is submitted as per sub-paragraphs (a) or (b) of Sub-Clause 20.1, it is dealt with in accordance with Sub-Clause 20.2, which specifically covers claims for time and/or money. Part of the procedure under Sub-Clause 20.2 is for a payment and/or an extension of time-related claim to be agreed or determined by the Engineer/Employer’s Representative (in case of the FIDIC Silver Book) in accordance with Sub-Clause 3.7/3.5.

D.

The time bar only applies to Contractor’s Claims and not to Employer’s Claims.

Discussion
Page: 8 / 10

CCM
PDF

$36.75  $104.99

CCM Testing Engine

$43.75  $124.99

CCM PDF + Testing Engine

$57.75  $164.99