Comprehensive and Detailed 250 to 250 words of Explanation From Exact Extract of SAFe 6.0, including the SAFe Release domains:
In SAFe 6.0, the Team Sync is a key ART-level event facilitated by the Release Train Engineer (RTE) and is explicitly designed to keep the Agile Release Train on track during Program Increment execution. The Team Sync replaces the traditional Scrum of Scrums and is a short, frequent coordination event where team representatives discuss progress, dependencies, impediments, and risks. Its purpose is to ensure alignment across teams and enable fast problem-solving to maintain flow.
SAFe guidance states that the Team Sync focuses on how teams are progressing toward PI Objectives, what issues may impact delivery, and what coordination is needed to address cross-team dependencies. By making problems visible early, the RTE can facilitate timely decision-making and escalation when needed. This directly supports the Release domain’s emphasis on transparency, alignment, and predictable execution.
The other options do not serve this purpose. Solution Demos are facilitated at the Solution level to demonstrate integrated solution increments. Iteration Reviews occur at the team level and focus on team progress. Coach Sync is used to align Scrum Masters and Team Coaches on systemic improvement actions, not to manage day-to-day ART execution.
Therefore, the Team Sync is the RTE-facilitated event designed to keep the ART on the tracks throughout the PI.