Question 76

Which of the following BEST describes the relationship between test planning and test execution? [K2]

Options:

A.

Test planning ensures the level of detail in test procedures is appropriate for test execution

B.

Test planning schedules test execution but does not assign resources

C.

Test planning defines the overall approach to testing but does not schedule specific activities such as test execution

D.

Test planning identifies test objectives related to scope and risk but does not define the level of detail for test procedures used in test execution

Discussion
Hassan
Highly Recommended Dumps… today I passed my exam! Same questions appear. I bought Full Access.
Kasper Oct 20, 2024
Hey wonderful….so same questions , sounds good. Planning to write this week, I will go for full access today.
Ayra
How these dumps are necessary for passing the certification exam?
Damian Oct 22, 2024
They give you a competitive edge and help you prepare better.
Walter
Yayyy!!! I passed my exam with the help of Cramkey Dumps. Highly appreciated!!!!
Angus Nov 4, 2024
YES….. I saw the same questions in the exam.
Joey
I highly recommend Cramkey Dumps to anyone preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Dexter Aug 7, 2024
Agreed. It's definitely worth checking out if you're looking for a comprehensive and reliable study resource.
Question 77

Which of the following are 'Exit Criteria?'

Options:

A.

Acceptance criteria, completion criteria, pass/fail criteria.

B.

Coverage of code, schedule, estimates of defect density.

C.

The last executable statement within a component.

D.

Cost overruns.

Discussion
Question 78

Which of the following metrics could be used to monitor progress along with test preparation and execution? [K1]

Options:

A.

The total number of tests planned

B.

The total number of requirements to be tested

C.

The failure rate in testing already completed

D.

The number of testers used for test execution so far

Discussion
Question 79

Which of the following would typically be identified using static analysis by tools? [K1]

Options:

A.

Spelling mistake on an error message

B.

A potential infinite loop

C.

Memory leakage

D.

A variable set to the wrong value

Discussion