Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

CIPS Updated L4M3 Exam Questions and Answers by youssef

Page: 12 / 17

CIPS L4M3 Exam Overview :

Exam Name: Commercial Contracting
Exam Code: L4M3 Dumps
Vendor: CIPS Certification: CIPS Level 4 Diploma in Procurement and Supply
Questions: 233 Q&A's Shared By: youssef
Question 48

GPP, the employer, and Prosolia UK, the contractor, entered into five EPC contracts for the development of five different solar power generation plants in the United Kingdom. Four out of the five developments failed to be commissioned by the relevant due dates, with the delays ranging from 44 to 285 days.

Among other claims, GPP, acting through its two investment vehicles, claimed liquidated damages of £500 per day in all four contracts for Prosolia UK's failure to achieve completion of the plants by the due date. The liquidated damages claimed amounted to £1,804,221 across the four delayed contracts.

Prosolia, alongside various other defences, raised the defence that the liquidated damages provision in each contract was a penalty, and therefore unenforceable against it. Is Prosolia contractually obliged to make the payment to the plaintiff?

Options:

A.

No, the amount claimed is too excessive and it may put Prosolia into insolvency. The clause must be void

B.

No, the clause must be treated as a penalty clause which is unenforceable in UK

C.

Yes, the amount is a reward to the employer as they have supervised and monitored the projects

D.

Yes, the clause is a genuine estimate of possible losses that GPP may have suffered and therefore, it is enforceable.

Discussion
Question 49

John is a new procurement manager who has recently joined Smiths Facilities Management Ltd. The company provides maintenance services through the utilisation of subcontractors. It is experiencing a number of issues with its supply chain which has resulted in customer complaints, and John would like to introduce service level agreements (SLAs) to some of its key providers. Which of the following should be included?

    How often the service will be provided

    The procedures to be followed to resolve disputes

    The qualifications needed by staff providing the service

    The stock maintained by the subcontractor

Options:

A.

1, 3 and 4 only

B.

2, 3 and 4 only

C.

1, 2 and 4 only

D.

1, 2 and 3 only

Discussion
Conor
I recently used these dumps for my exam and I must say, I was impressed with their authentic material.
Yunus Jun 3, 2026
Exactly…….The information in the dumps is so authentic and up-to-date. Plus, the questions are very similar to what you'll see on the actual exam. I felt confident going into the exam because I had studied using Cramkey Dumps.
Anaya
I found so many of the same questions on the real exam that I had already seen in the Cramkey Dumps. Thank you so much for making exam so easy for me. I passed it successfully!!!
Nina Jun 4, 2026
It's true! I felt so much more confident going into the exam because I had already seen and understood the questions.
Hassan
Highly Recommended Dumps… today I passed my exam! Same questions appear. I bought Full Access.
Kasper Jun 4, 2026
Hey wonderful….so same questions , sounds good. Planning to write this week, I will go for full access today.
Inaaya
Are these Dumps worth buying?
Fraser Jun 26, 2026
Yes, of course, they are necessary to pass the exam. They give you an insight into the types of questions that could come up and help you prepare effectively.
Robin
Cramkey is highly recommended.
Jonah Jun 10, 2026
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Question 50

Rochdale Ltd is looking for a new IT system to automate some of its operations. In designing the specification, procurement manager supposes that it should be done solely by the IT department who have deep expertise on this matter. Is procurement manager’s opinion appropriate?

Options:

A.

No, because challenging the user's demand is the role of procurement

B.

Yes, because designing complex specification would waste procurement manager’s time

C.

Yes, because procurement professional has no expertise in IT sector

D.

No, because designing complex specification could only be outsourced

Discussion
Question 51

A senior buyer is preparing specification for the next purchase. He intends to embed social and environmental criteria that align with his organisation's overarching strategy. Which of the following provides the social and environmental objectives that an organisation pursues?

Options:

A.

Economic performance

B.

Procurement Systems and Technology

C.

Economy of scale

D.

Organisation’s CSR policies

Discussion
Page: 12 / 17
Title
Questions
Posted

L4M3
PDF

$36.75  $104.99

L4M3 Testing Engine

$43.75  $124.99

L4M3 PDF + Testing Engine

$57.75  $164.99