Summer Special Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: big60

CIPS Updated L4M3 Exam Questions and Answers by arielle

Page: 9 / 14

CIPS L4M3 Exam Overview :

Exam Name: Commercial Contracting
Exam Code: L4M3 Dumps
Vendor: CIPS Certification: CIPS Level 4 Diploma in Procurement and Supply
Questions: 196 Q&A's Shared By: arielle
Question 36

An example of a qualitative performance measure could be one that relates to opinions about the service quality of the supplier. Is this correct?

Options:

A.

Yes, this is often how satisfaction is measured

B.

No, this will relate to how much prices have increased by

C.

No, this type of measure will relate to the number of incomplete deliveries

D.

Yes, this will relate to the actual number of complaints received

Discussion
Question 37

When a supplier signs an insurance policy with an insurance company, which of the following is transferred to insurance company?

Options:

A.

Right

B.

Risk

C.

Legal responsibility

D.

Contractual obligation

Discussion
Pippa
I was so happy to see that almost all the questions on the exam were exactly what I found in their Dumps.
Anastasia Aug 27, 2025
You are right…It was amazing! The Cramkey Dumps were so comprehensive and well-organized, it made studying for the exam a breeze.
Ayra
How these dumps are necessary for passing the certification exam?
Damian Aug 17, 2025
They give you a competitive edge and help you prepare better.
Ava-Rose
Yes! Cramkey Dumps are amazing I passed my exam…Same these questions were in exam asked.
Ismail Aug 25, 2025
Wow, that sounds really helpful. Thanks, I would definitely consider these dumps for my certification exam.
Inaya
Passed the exam. questions are valid. The customer support is top-notch. They were quick to respond to any questions I had and provided me with all the information I needed.
Cillian Aug 1, 2025
That's a big plus. I've used other dump providers in the past and the customer support was often lacking.
Question 38

Which of the following shall help the purchaser control the selection of tier 2 suppliers?

Options:

A.

Subcontracting clause

B.

Warranty clause

C.

Guarantee clause

D.

Insurance clause

Discussion
Question 39

GPP, the employer, and Prosolia UK, the contractor, entered into five EPC contracts for the development of five different solar power generation plants in the United Kingdom. Four out of the five developments failed to be commissioned by the relevant due dates, with the delays ranging from 44 to 285 days.

Among other claims, GPP, acting through its two investment vehicles, claimed liquidated damages of £500 per day in all four contracts for Prosolia UK's failure to achieve completion of the plants by the due date. The liquidated damages claimed amounted to £1,804,221 across the four delayed contracts.

Prosolia, alongside various other defences, raised the defence that the liquidated damages provision in each contract was a penalty, and therefore unenforceable against it. Is Prosolia contractually obliged to make the payment to the plaintiff?

Options:

A.

No, the amount claimed is too excessive and it may put Prosolia into insolvency. The clause must be void

B.

No, the clause must be treated as a penalty clause which is unenforceable in UK

C.

Yes, the amount is a reward to the employer as they have supervised and monitored the projects

D.

Yes, the clause is a genuine estimate of possible losses that GPP may have suffered and therefore, it is enforceable.

Discussion
Page: 9 / 14

L4M3
PDF

$42  $104.99

L4M3 Testing Engine

$50  $124.99

L4M3 PDF + Testing Engine

$66  $164.99