Question 36

An example of a qualitative performance measure could be one that relates to opinions about the service quality of the supplier. Is this correct?

Options:

A.

Yes, this is often how satisfaction is measured

B.

No, this will relate to how much prices have increased by

C.

No, this type of measure will relate to the number of incomplete deliveries

D.

Yes, this will relate to the actual number of complaints received

Discussion
Kingsley
Do anyone guide my how these dumps would be helpful for new students like me?
Haris Oct 24, 2025
Absolutely! They are highly recommended for anyone looking to pass their certification exam. The dumps are easy to understand and follow, making it easier for you to study and retain the information.
Neve
Will I be able to achieve success after using these dumps?
Rohan Oct 9, 2025
Absolutely. It's a great way to increase your chances of success.
Miriam
Highly recommended Dumps. 100% authentic and reliable. Passed my exam with wonderful score.
Milan Oct 15, 2025
I see. Thanks for the information. I'll definitely keep Cramkey in mind for my next exam.
Ella-Rose
Amazing website with excellent Dumps. I passed my exam and secured excellent marks!!!
Alisha Oct 2, 2025
Extremely accurate. They constantly update their materials with the latest exam questions and answers, so you can be confident that what you're studying is up-to-date.
Question 37

When a supplier signs an insurance policy with an insurance company, which of the following is transferred to insurance company?

Options:

A.

Right

B.

Risk

C.

Legal responsibility

D.

Contractual obligation

Discussion
Question 38

Which of the following shall help the purchaser control the selection of tier 2 suppliers?

Options:

A.

Subcontracting clause

B.

Warranty clause

C.

Guarantee clause

D.

Insurance clause

Discussion
Question 39

GPP, the employer, and Prosolia UK, the contractor, entered into five EPC contracts for the development of five different solar power generation plants in the United Kingdom. Four out of the five developments failed to be commissioned by the relevant due dates, with the delays ranging from 44 to 285 days.

Among other claims, GPP, acting through its two investment vehicles, claimed liquidated damages of £500 per day in all four contracts for Prosolia UK's failure to achieve completion of the plants by the due date. The liquidated damages claimed amounted to £1,804,221 across the four delayed contracts.

Prosolia, alongside various other defences, raised the defence that the liquidated damages provision in each contract was a penalty, and therefore unenforceable against it. Is Prosolia contractually obliged to make the payment to the plaintiff?

Options:

A.

No, the amount claimed is too excessive and it may put Prosolia into insolvency. The clause must be void

B.

No, the clause must be treated as a penalty clause which is unenforceable in UK

C.

Yes, the amount is a reward to the employer as they have supervised and monitored the projects

D.

Yes, the clause is a genuine estimate of possible losses that GPP may have suffered and therefore, it is enforceable.