Question 36

Cooling tower blowdown is necessary because

Options:

A.

too much water in the system is inefficient so its water levels must be lowered

B.

a buildup of dissolved solids increases conductivity which decreases efficiency

C.

excess water treatment chemical levels corrode pipes and bleed-off reduces chemical levels

D.

cold temperatures can freeze pipes if water is not moved and bleed-off prevents that from happening

Discussion
Cecilia
Yes, I passed my certification exam using Cramkey Dumps.
Helena Jun 24, 2026
Great. Yes they are really effective
Lennox
Something Special that they provide a comprehensive overview of the exam content. They cover all the important topics and concepts, so you can be confident that you are well-prepared for the test.
Aiza Jun 1, 2026
That makes sense. What makes Cramkey Dumps different from other study materials?
Mylo
Excellent dumps with authentic information… I passed my exam with brilliant score.
Dominik Jun 16, 2026
That's amazing! I've been looking for good study material that will help me prepare for my upcoming certification exam. Now, I will try it.
Stefan
Thank you so much Cramkey I passed my exam today due to your highly up to date dumps.
Ocean Jun 20, 2026
Agree….Cramkey Dumps are constantly updated based on changes in the exams. They also have a team of experts who regularly review the materials to ensure their accuracy and relevance. This way, you can be sure you're studying the most up-to-date information available.
Question 37

Which of the following strategies improves cooling tower water efficiency?

Options:

A.

Increase cooling tower fan speed

B.

Increase the cooling tower blowdown

C.

Install and maintain a conductivity meter

D.

Lower set point of water leaving cooling tower

Discussion
Question 38

Using the following table, the number of cooling tower cycles in Water Efficiency Credit, Cooling Tower Water Use is determined by which five parameters in the rating system?(Click on Exhibit)

Options:

A.

All of the five parameters summed together

B.

All of the five parameters subtracted from the maximum concentration level

C.

Whichever of the five parameters has the fewest calculated cycles of concentration without exceeding the maximum level for the parameter

D.

Whichever of the five parameters has the greatest calculated cycles of concentration without exceeding the maximum level for the parameter

Discussion
Question 39

At what point is it appropriate for the LEED AP to administer an alternative transportation survey to those that visit the building?

Options:

A.

When 50% of visitors utilize alternative transportation modes to visit the building

B.

When 80% of visitors utilize alternative transportation modes to visit the building

C.

When the daily average or typical peak number of visitors is at least 50% of the regular building occupants

D.

When the daily average or typical peak number of visitors is greater than the number of regular buildingoccupants

Discussion