Question 36

Cooling tower blowdown is necessary because

Options:

A.

too much water in the system is inefficient so its water levels must be lowered

B.

a buildup of dissolved solids increases conductivity which decreases efficiency

C.

excess water treatment chemical levels corrode pipes and bleed-off reduces chemical levels

D.

cold temperatures can freeze pipes if water is not moved and bleed-off prevents that from happening

Discussion
Anaya
I found so many of the same questions on the real exam that I had already seen in the Cramkey Dumps. Thank you so much for making exam so easy for me. I passed it successfully!!!
Nina Dec 25, 2025
It's true! I felt so much more confident going into the exam because I had already seen and understood the questions.
Nell
Are these dumps reliable?
Ernie Dec 16, 2025
Yes, very much so. Cramkey Dumps are created by experienced and certified professionals who have gone through the exams themselves. They understand the importance of providing accurate and relevant information to help you succeed.
Norah
Cramkey is highly recommended.
Zayan Dec 22, 2025
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Ava-Rose
Yes! Cramkey Dumps are amazing I passed my exam…Same these questions were in exam asked.
Ismail Dec 11, 2025
Wow, that sounds really helpful. Thanks, I would definitely consider these dumps for my certification exam.
Question 37

Which of the following strategies improves cooling tower water efficiency?

Options:

A.

Increase cooling tower fan speed

B.

Increase the cooling tower blowdown

C.

Install and maintain a conductivity meter

D.

Lower set point of water leaving cooling tower

Discussion
Question 38

Using the following table, the number of cooling tower cycles in Water Efficiency Credit, Cooling Tower Water Use is determined by which five parameters in the rating system?(Click on Exhibit)

Options:

A.

All of the five parameters summed together

B.

All of the five parameters subtracted from the maximum concentration level

C.

Whichever of the five parameters has the fewest calculated cycles of concentration without exceeding the maximum level for the parameter

D.

Whichever of the five parameters has the greatest calculated cycles of concentration without exceeding the maximum level for the parameter

Discussion
Question 39

At what point is it appropriate for the LEED AP to administer an alternative transportation survey to those that visit the building?

Options:

A.

When 50% of visitors utilize alternative transportation modes to visit the building

B.

When 80% of visitors utilize alternative transportation modes to visit the building

C.

When the daily average or typical peak number of visitors is at least 50% of the regular building occupants

D.

When the daily average or typical peak number of visitors is greater than the number of regular buildingoccupants

Discussion