Summer Special Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: big60

Scrum Updated PSM-I Exam Questions and Answers by ciaran

Page: 18 / 19

Scrum PSM-I Exam Overview :

Exam Name: Professional Scrum Master I
Exam Code: PSM-I Dumps
Vendor: Scrum Certification: Professional Scrum Master
Questions: 268 Q&A's Shared By: ciaran
Question 72

Which statement best describes the Sprint Review?

Options:

A.

It is used to congratulate the Development Team if it did what it forecast, or to punish the Development Team if it failed to meet its forecast.

B.

It is a demo at the end of the Sprint for everyone in the organization to check on the work done.

C.

It is a mechanism to control the Development Team’s activities during a Sprint.

D.

It is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out what to do next.

Discussion
Question 73

The Daily Scrum is an event that happens every day. What would be three key concerns if the frequency were to be lowered to every two or three days? (Choose three.)

Options:

A.

Opportunities to insect and adapt the Sprint Backlog are lost.

B.

Impediments are raised and resolved more slowly.

C.

The Product Owner cannot accurately report progress to the stakeholders.

D.

Too much work is spent updating the Scrum board before the meeting.

E.

The Scrum Master loses the ability to update the Gantt chart properly.

F.

The Sprint plan may become inaccurate.

Discussion
Question 74

The CEO asks the Developers to add a "very important" item to a Sprint that is in progress.

What should the Developers do?

(choose the best answer)

Options:

A.

Add the item to the Sprint Backlog for the next Sprint.

B.

Add the item to the top of the Product Backlog.

C.

Add the item to the current Sprint Backlog and begin work immediately since the

request came from the CEO.

D.

Add the item to the current Sprint and drop an item of equal size.

E.

Discuss the item with the other members of the Scrum Team so the team can

decide what to do.

Discussion
Question 75

During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?

Options:

A.

When the Product Owner identifies new work.

B.

As soon as possible after they are identified.

C.

When the Scrum Master has time to enter them.

D.

During the Daily Scrum after the Development Team approves them.

Discussion
Cody
I used Cramkey Dumps to prepare and a lot of the questions on the exam were exactly what I found in their study materials.
Eric Aug 26, 2025
Really? That's great to hear! I used Cramkey Dumps too and I had the same experience. The questions were almost identical.
Wyatt
Passed my exam… Thank you so much for your excellent Exam Dumps.
Arjun Aug 18, 2025
That sounds really useful. I'll definitely check it out.
Josie
I just passed my certification exam using their dumps and I must say, I was thoroughly impressed.
Fatimah Aug 14, 2025
You’re right. The dumps were authentic and covered all the important topics. I felt confident going into the exam and it paid off.
Addison
Want to tell everybody through this platform that I passed my exam with excellent score. All credit goes to Cramkey Exam Dumps.
Libby Aug 4, 2025
That's good to know. I might check it out for my next IT certification exam. Thanks for the info.
Page: 18 / 19
Title
Questions
Posted

PSM-I
PDF

$42  $104.99

PSM-I Testing Engine

$50  $124.99

PSM-I PDF + Testing Engine

$66  $164.99