Weekend Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cram70off

Scrum Updated PSM-I Exam Questions and Answers by ciaran

Page: 18 / 19

Scrum PSM-I Exam Overview :

Exam Name: Professional Scrum Master I
Exam Code: PSM-I Dumps
Vendor: Scrum Certification: Professional Scrum Master
Questions: 268 Q&A's Shared By: ciaran
Question 72

Which statement best describes the Sprint Review?

Options:

A.

It is used to congratulate the Development Team if it did what it forecast, or to punish the Development Team if it failed to meet its forecast.

B.

It is a demo at the end of the Sprint for everyone in the organization to check on the work done.

C.

It is a mechanism to control the Development Team’s activities during a Sprint.

D.

It is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out what to do next.

Discussion
Question 73

The Daily Scrum is an event that happens every day. What would be three key concerns if the frequency were to be lowered to every two or three days? (Choose three.)

Options:

A.

Opportunities to insect and adapt the Sprint Backlog are lost.

B.

Impediments are raised and resolved more slowly.

C.

The Product Owner cannot accurately report progress to the stakeholders.

D.

Too much work is spent updating the Scrum board before the meeting.

E.

The Scrum Master loses the ability to update the Gantt chart properly.

F.

The Sprint plan may become inaccurate.

Discussion
Question 74

The CEO asks the Developers to add a "very important" item to a Sprint that is in progress.

What should the Developers do?

(choose the best answer)

Options:

A.

Add the item to the Sprint Backlog for the next Sprint.

B.

Add the item to the top of the Product Backlog.

C.

Add the item to the current Sprint Backlog and begin work immediately since the

request came from the CEO.

D.

Add the item to the current Sprint and drop an item of equal size.

E.

Discuss the item with the other members of the Scrum Team so the team can

decide what to do.

Discussion
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Jan 24, 2026
Yeah, definitely. I experienced the same.
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Jan 2, 2026
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Elise
I've heard that Cramkey is one of the best websites for exam dumps. They have a high passing rate and the questions are always up-to-date. Is it true?
Cian Jan 9, 2026
Definitely. The dumps are constantly updated to reflect the latest changes in the certification exams. And I also appreciate how they provide explanations for the answers, so I could understand the reasoning behind each question.
Ernest
That's amazing. I think I'm going to give Cramkey Dumps a try for my next exam. Thanks for telling me about them! CramKey admin please share more questions……You guys are amazing.
Nate Jan 4, 2026
I failed last week, I never know this site , but amazed to see all these questions were in my exam week before. I feel bad now, why I didn’t bother this site. Thanks Cramkey, Excellent Job.
Question 75

During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?

Options:

A.

When the Product Owner identifies new work.

B.

As soon as possible after they are identified.

C.

When the Scrum Master has time to enter them.

D.

During the Daily Scrum after the Development Team approves them.

Discussion
Page: 18 / 19
Title
Questions
Posted

PSM-I
PDF

$31.5  $104.99

PSM-I Testing Engine

$37.5  $124.99

PSM-I PDF + Testing Engine

$49.5  $164.99