Question 48

Which two activities will a Product Owner engage in during a Sprint? (Choose two.)

Options:

A.

Run the Daily Scrum.

B.

Prioritize the Development Team’s work on the Sprint Backlog.

C.

Update management on what is being worked on.

D.

Answer QUESTION NO:s from the Development Team about items in the current Sprint.

Discussion
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Sep 5, 2026
Yeah, definitely. I experienced the same.
Sam
Can I get help from these dumps and their support team for preparing my exam?
Audrey Sep 25, 2026
Definitely, you won't regret it. They've helped so many people pass their exams and I'm sure they'll help you too. Good luck with your studies!
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony Sep 16, 2026
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Nia
Why are these Dumps so important for students these days?
Mary Sep 27, 2026
With the constantly changing technology and advancements in the industry, it's important for students to have access to accurate and valid study material. Cramkey Dumps provide just that. They are constantly updated to reflect the latest changes and ensure that the information is up-to-date.
Question 49

A Scrum Master is keeping a list of open impediments, but it is growing and he/she has been able to resolve only a small portion of the impediments. Which three techniques would be most helpful in this situation? (Choose three.)

Options:

A.

Consulting with the Development Team.

B.

Prioritizing the list and working on them in order.

C.

Arranging a triage meeting with all project managers.

D.

Alerting management to the impediments and their impact.

Discussion
Question 50

(When might a Sprint be cancelled?

Choose the best answer.)

Options:

A.

When the Sprint Goal becomes obsolete.

B.

When the sales department has an important new opportunity.

C.

When the Developers determine the product plan is infeasible.

D.

When it becomes clear that not everything will be finished by the end of the Sprint.

Discussion
Question 51

(When multiple Scrum Teams are working on a single product, what best describes the Definition of Done?

Choose the best answer.)

Options:

A.

When multiple Scrum Teams are working together on a product, they must mutually define and comply with the same Definition of Done.

B.

Each Scrum Team defines and uses its own. The differences are discussed and reconciled during a hardening Sprint.

C.

Each Scrum Team uses its own, but must make their definition clear to all other teams so the differences are known.

D.

The Scrum Masters from each Scrum Team define a common Definition of Done.

Discussion