Question 24

Defect Management

Consider a defect report and assume that a part of its lifecycle includes the following states:

New: Is the initial state

Working: Means that the developers are addressing the defect in order to produce a fix for the defect

Clarification: Means that the developers need more information from the tester to address the defect and produce a fix for the defect and the tester is working to provide this information to the developers

Verification: Means that a fix for the defect has been produced and the tester is running the adequate tests to verify whether the fix solves the defect

Closed: is the final state

Which of the following answers represents an invalid sequence of states that can’t lead the bug report to the “Closed” state?

Number of correct responses: 1

K21 credit

Options:

A.

New, Working, Verification, Working, Clarification, Working, Verification, Closed

B.

New, Working, Clarification, Working, Verification, Closed

C.

New, Working, Verification, Working, Clarification, Working, Closed

D.

New, Working, Verification, Closed

Discussion
Josephine
I want to ask about their study material and Customer support? Can anybody guide me?
Zayd May 10, 2026
Yes, the dumps or study material provided by them are authentic and up to date. They have a dedicated team to assist students and make sure they have a positive experience.
Rosalie
I passed. I would like to tell all students that they should definitely give Cramkey Dumps a try.
Maja May 6, 2026
That sounds great. I'll definitely check them out. Thanks for the suggestion!
Peyton
Hey guys. Guess what? I passed my exam. Thanks a lot Cramkey, your provided information was relevant and reliable.
Coby May 22, 2026
Thanks for sharing your experience. I think I'll give Cramkey a try for my next exam.
Georgina
I used Cramkey Dumps to prepare for my recent exam and I have to say, they were a huge help.
Corey May 19, 2026
Really? How did they help you? I know these are the same questions appears in exam. I will give my try. But tell me if they also help in some training?
Alaia
These Dumps are amazing! I used them to study for my recent exam and I passed with flying colors. The information in the dumps is so valid and up-to-date. Thanks a lot!!!
Zofia May 28, 2026
That's great to hear! I've been struggling to find good study material for my exam. I will ty it for sure.
Question 25

Test Management

Which one of the following metrics to be produced needs traceability between the test cases and each item in a proper test basis?

Number of correct responses: 1

K21 credit

Options:

A.

Requirements coverage

B.

Trends in the lag time from defect reporting to resolution

C.

Mean time between failures for the system

D.

Cumulative number of reported defects versus cumulative number of resolved defects

Discussion
Question 26

Improving the Testing Process

Which of the following statements about the STEP test process improvement model is true?

Number of correct responses: 1

K21 credit

Options:

A.

In the STEP model, tests validate the requirements and use cases when they are developed

B.

The STEP model stresses defect detection and demonstration of capability, whereas the defect prevention is a secondary potential goal of testing

C.

The STEP model assures that the system requirements specification and the test design specification processes don't overlap

D.

In the STEP model, testware design occurs after coding

Discussion
Question 27

Improving the Testing Process

Which of the following statements about the TMMi test process improvement model is true?

Number of correct responses: 1

K21 credit

Options:

A.

In TMMi all the process areas at lower levels must be 75% complete by achieving specific and generic goals in order to claim the higher level

B.

TMMi provides an approach for test process improvement such as the IDEAL (Initiating, Diagnosing, Establishing, Acting and Learning) model

C.

TMMi has a staged architecture for process improvement with seven maturity levels

D.

At TMMi level 1 testing is chaotic without a defined process, and it is often seen as the same as debugging