Question 12

A data center scores Rated-3 in mechanical, Rated-4 in electrical, and Rated-2 in architectural.

What is the overall Rating of this data center when the Rating is based on the ANSI/TIA-942?

Options:

A.

Rated-2 since that is the lowest rating received

B.

Rated-4 since that is the highest rating received

C.

Rated-4 since electrical is more important than mechanical and architectural

D.

Depends on the Rating scored in telecommunications

Discussion
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Dec 2, 2025
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Lois
I passed my exam with wonderful score. Their dumps are 100% valid and I felt confident during the exam.
Ernie Dec 8, 2025
Absolutely. The best part is, the answers in the dumps were correct. So, I felt confident and well-prepared for the exam.
Josephine
I want to ask about their study material and Customer support? Can anybody guide me?
Zayd Dec 4, 2025
Yes, the dumps or study material provided by them are authentic and up to date. They have a dedicated team to assist students and make sure they have a positive experience.
Ilyas
Definitely. I felt much more confident and prepared because of the Cramkey Dumps. I was able to answer most of the questions with ease and I think that helped me to score well on the exam.
Saoirse Dec 20, 2025
That's amazing. I'm glad you found something that worked for you. Maybe I should try them out for my next exam.
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson Dec 5, 2025
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Question 13

A data center is in an area where utility power is highly available—only a few outages per year, typically <1 hour per event and <50 hours/year not available. What type of generators should be installed?

Options:

A.

Continuous generators in at least N+1

B.

A combination of standby, prime, and continuous sized to 500% of the load

C.

Standby generators; no N+1 needed as the risk of a failure to start is negligible

D.

Standby generators, ideally in an N+1 configuration

Discussion
Question 14

A new network storage device in a non-standard size rack of approximately 600 kg/1,300 lbs is going to be installed in the data center.

Are new floor loading calculations required?

Options:

A.

No, as long as the equipment is less than 700 kg/1,500 lbs it will be within the limits.

B.

No, specifications of equipment brought into the data center will already be known during the design of the data center, and therefore the floor will be able to handle it.

C.

Yes, additional floor loading calculations need to be done by the floor manager, which should be verified by the safety engineer.

D.

Yes, a structural engineer, approved/endorsed by the building owner, should carry out new floor loading calculations.

Discussion
Question 15

When designing a data center network, your company wants to minimize the number of network switches to manage.

What type of physical cabling layout would be the best choice?

Options:

A.

ToR (Top of Rack) design

B.

EoR (End of Row) design

C.

Star network design using coaxial cables

D.

It does not matter as the number of switches is not influenced by the physical cabling layout