Question 28

A data center is located in an area where the demand for power is higher than the utility power company is able to deliver. This results in frequent power outages and, therefore, power shedding (scheduled/controlled power shutdown for areas) is frequently applied. The mains power is more than 650 hours/year not available.

What type of generators should be installed?

Options:

A.

Standby generators should be installed in at least an N+1 configuration

B.

Continuous generators should be installed, at least in an N+1 configuration

C.

A combination of standby-, prime-, and continuous-generators, as the duration of the power outage is unpredictable. The total available capacity of the generators should be at least 500% of the data center load

D.

Continuous generators should be installed; no N+1 configuration is needed as the generators will run all the time

Discussion
Cecilia
Yes, I passed my certification exam using Cramkey Dumps.
Helena Feb 24, 2026
Great. Yes they are really effective
Josie
I just passed my certification exam using their dumps and I must say, I was thoroughly impressed.
Fatimah Feb 10, 2026
You’re right. The dumps were authentic and covered all the important topics. I felt confident going into the exam and it paid off.
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella Feb 18, 2026
That's great. I think I'll give Cramkey Dumps a try.
Vienna
I highly recommend them. They are offering exact questions that we need to prepare our exam.
Jensen Feb 20, 2026
That's great. I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Kingsley
Do anyone guide my how these dumps would be helpful for new students like me?
Haris Feb 19, 2026
Absolutely! They are highly recommended for anyone looking to pass their certification exam. The dumps are easy to understand and follow, making it easier for you to study and retain the information.
Question 29

Where should raised-floor installation start?

Options:

A.

Point A (entrance corner)

B.

Point B (side wall)

C.

Point C (center of the room)

D.

Point D (corner opposite entrance)

Discussion
Question 30

Which gas-based system in general requires a larger amount of gas in order to be effective, a halocarbon gas-based fire suppression system or an inert gas-based fire suppression system?

Options:

A.

Inert gas requires a smaller amount of gas compared to halocarbon gas

B.

Inert gas requires a larger amount of gas compared to halocarbon gas

C.

Inert gas and halocarbon gas require the same amount of gas

D.

Impossible to answer without knowing the temperature

Discussion
Question 31

ICT rack consumes 3 kW with ΔT ~11 °C (20 °F). Calculate required airflow (CFM).

Options:

A.

~1,500 CFM

B.

~1,000 CFM

C.

~500 CFM

D.

~160 CFM