Question 16

An R&D group director approves a major program's charter although the director has a high level of understanding of the program's scope (hoy are unsure of how the program manager can be successful in delivering the program's commitments

What should the program manager do to align stakeholders with planning and monitoring the program's progress?

Options:

A.

Establish high-level program milestones

B.

Develop an accountability matrix, and assign program roles and responsibilities

C.

Generate a supplier management plan to identify external stakeholders

D.

Create a communications management plan, and establish reporting formats

Discussion
Georgina
I used Cramkey Dumps to prepare for my recent exam and I have to say, they were a huge help.
Corey Oct 2, 2024
Really? How did they help you? I know these are the same questions appears in exam. I will give my try. But tell me if they also help in some training?
Esmae
I highly recommend Cramkey Dumps to anyone preparing for the certification exam.
Mollie Aug 15, 2024
Absolutely. They really make it easier to study and retain all the important information. I'm so glad I found Cramkey Dumps.
Nylah
I've been looking for good study material for my upcoming certification exam. Need help.
Dolly Oct 3, 2024
Then you should definitely give Cramkey Dumps a try. They have a huge database of questions and answers, making it easy to study and prepare for the exam. And the best part is, you can be sure the information is accurate and relevant.
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Aug 9, 2024
Yeah, definitely. I experienced the same.
Question 17

The program manager defines the program objectives, requirements and develops a high-level road map. To ensure program alignment with the enterprise strategic plan the program manager should work with which of the following?

Options:

A.

Program governance board

B.

Program management office

C.

Change control board

D.

Project managers on the program

Discussion
Question 18

The program manager plans to address a negative cost variance generating a red flag in the program management status report. What should the program manager do?

Options:

A.

Contact the project sponsors to present the details, impacts, and possible corrective actions regarding the negative cost variance

B.

Gather all the details, analyze impacts, determine corrective actions and present the findings to the governance board for direction

C.

Work with program sponsor to compile impact analysis data to obtain additional funding for the program

D.

Ask the program team to compile all details, analyze impacts, determine corrective actions and present to the governance board for direction

Discussion
Question 19

A program to implement a new payroll processing system at a healthcare company is nearing completion and is under budget. What should the program manager do next?

Options:

A.

Request permission from the program governance board to initiate program closure activities

B.

Present additional opportunities to the program sponsor

C.

Apply the remaining budget to operational activities

D.

Apply the remaining budget to deferred enhancement requests

Discussion