Question 36

The program selection committee presents several programs for approval:

Questions 36

Which program was selected based solely on a three-year return on investment?

Options:

A.

Program A

B.

Program B

C.

Program C

D.

Program D

Discussion
Alessia
Amazing Dumps. Found almost all questions in actual exam whih I prepared from these valuable dumps. Recommended!!!!
Belle Jan 4, 2026
That's impressive. I've been struggling with finding good study material for my certification. Maybe I should give Cramkey Dumps a try.
Miley
Hey, I tried Cramkey Dumps for my IT certification exam. They are really awesome and helped me pass my exam with wonderful score.
Megan Jan 27, 2026
That’s great!!! I’ll definitely give it a try. Thanks!!!
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Jan 24, 2026
Thanks for the recommendation! I'll check it out.
Madeleine
Passed my exam with my dream score…. Guys do give these dumps a try. They are authentic.
Ziggy Jan 22, 2026
That's really impressive. I think I might give Cramkey Dumps a try for my next certification exam.
Question 37

Questions 37

The above performance report shows the earned value (EV) analysis for a program The program director performs a high-level analysis and must present a summary narrative to the steering committee

What do the current findings show?

Options:

A.

Project C is running behind schedule and is over budget, projects A, B and D are on schedule

B.

Project A is running ahead of schedule and is under budget projects B, C and D are behind schedule

C.

The overall program is performing within an acceptable level of variance

D.

Project A is running behind schedule and is over budget projects B, C. and D are on schedule

Discussion
Question 38

In which phase of the protect design would an ICT distribution designer be expected to prepare preliminary cost estimates?

Options:

A.

CD

B.

SD

C.

PD

D.

DD

Discussion
Question 39

The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation. The program manager reviews the program resource management plan determine that project. A can wait until the resource becomes available, and assigns the resource to project B.

This is an example of which of the following?

Options:

A.

Program resource management planning

B.

Program risk mitigation

C.

Resource interdependency management

D.

Project resource planning