Week End Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

BICSI Updated RCDDv14 Exam Questions and Answers by effy

Page: 2 / 10

BICSI RCDDv14 Exam Overview :

Exam Name: BICSI Registered Communications Distribution Designer – RCDDv14
Exam Code: RCDDv14 Dumps
Vendor: BICSI Certification: RCDD Certification
Questions: 288 Q&A's Shared By: effy
Question 8

A two-year program is coming to an end Many of the initial governance board members have moved from their current posts or left the company Several new members have joined but have a shod association with the program, which changes the board's expectations and focus. During the final phase gate review, some board members are uncertain of their roles and expectations in the process.

How should the program manager handle this situation?

Options:

A.

Review the final program outcome with the program sponsor

B.

Prepare a program change request utilizing new board member input

C.

Review the strategic plan and benefits management plan with the board

D.

Present the final program status, costs, and schedule reports

Discussion
Question 9

The number of emerging risks increases in a component project and the program manager tails behind in reviewing) and approving the plans. This Impacts the component project manager's ability to effectively address the risks.

In this situation, what should the program manager change about the risk management plan?

Options:

A.

Allow the component project manager to delegate risk management responsibilities

B.

Assign the resolution of project-level risks to the component project manager

C.

Include risk escalation policies and procedures in the risk response plan

D.

Increase flexibility with risks that require a risk response

Discussion
Norah
Cramkey is highly recommended.
Zayan Jan 1, 2026
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Stefan
Thank you so much Cramkey I passed my exam today due to your highly up to date dumps.
Ocean Jan 9, 2026
Agree….Cramkey Dumps are constantly updated based on changes in the exams. They also have a team of experts who regularly review the materials to ensure their accuracy and relevance. This way, you can be sure you're studying the most up-to-date information available.
Walter
Yayyy!!! I passed my exam with the help of Cramkey Dumps. Highly appreciated!!!!
Angus Jan 15, 2026
YES….. I saw the same questions in the exam.
Josephine
I want to ask about their study material and Customer support? Can anybody guide me?
Zayd Jan 22, 2026
Yes, the dumps or study material provided by them are authentic and up to date. They have a dedicated team to assist students and make sure they have a positive experience.
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Jan 24, 2026
Thanks for the recommendation! I'll check it out.
Question 10

A program manager for the construction of a ship reviews the program management plan with a shipyard representative. The shipyard representative indicates that while 65 percent progress was anticipated only 60 percent has been achieved

What should the program manager do to ensure benefits realization?

Options:

A.

Conduct a program performance analysis based upon the deviation, and update the program business case to reflect the schedule delay

B.

Inform the program sponsor and the steering committee of the delay, and validate the program business case

C.

Analyze the impact of the delay, review risks, identify any corrective actions, and update the benefits management plan

D.

Update the program schedule, and escalate the issue to the program management office (PMO) to accelerate shipyard work.

Discussion
Question 11

A project's installation start involves a Kickoff Meeting and the General Contractor's Coordination Meeting. As part of the designer's responsibilities, which two of the following ate key elements of the Kick-off Meeting? (Select two options.)

Options:

A.

Project submittal approval process

B.

RFI process

C.

Payment procedures

D.

Punch List process

E.

Project start and completion dates

Discussion
Page: 2 / 10

RCDDv14
PDF

$36.75  $104.99

RCDDv14 Testing Engine

$43.75  $124.99

RCDDv14 PDF + Testing Engine

$57.75  $164.99