Question 28

Questions 28

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the cost of manufacturing labor for the piece of equipment today?

Options:

A.

$140,000

B.

$875,000

C.

$210,000

D.

$105,000

Discussion
Question 29

AACE International defines _____________as a technique of economic evaluation that sums over a given study period, the costs of initial investment, replacements, operations, and maintenance/repair; expressed in either present or annual value terms.

Options:

A.

Risk analysis

B.

Benefit/Cost ratio (B/C) method

C.

Net present worth method

D.

Life cycle costs method (LCC)

Discussion
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Dec 19, 2025
Yeah, definitely. I experienced the same.
Sam
Can I get help from these dumps and their support team for preparing my exam?
Audrey Dec 15, 2025
Definitely, you won't regret it. They've helped so many people pass their exams and I'm sure they'll help you too. Good luck with your studies!
Stefan
Thank you so much Cramkey I passed my exam today due to your highly up to date dumps.
Ocean Dec 13, 2025
Agree….Cramkey Dumps are constantly updated based on changes in the exams. They also have a team of experts who regularly review the materials to ensure their accuracy and relevance. This way, you can be sure you're studying the most up-to-date information available.
Alaya
Best Dumps among other dumps providers. I like it so much because of their authenticity.
Kaiden Dec 28, 2025
That's great. I've used other dump providers in the past and they were often outdated or had incorrect information. This time I will try it.
Question 30

Questions 30

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

The entire pipe has been received, hangers have been installed, and all pipes are in place. None has been welded or flushed. What percent complete is this project?

Options:

A.

45%

B.

50%

C.

95%

D.

30%

Discussion
Question 31

If a project is said to be on a "fast track program/' the fast track method is:

Options:

A.

Simultaneous working engineering, procurement, and construction, with appropriate overlap from each phase of work so that delays are eliminated and all the work is streamlined into a correct plan of logic/sequence and duration for all of the work

B.

First completing engineering and procurement, then executing construction

C.

Analyzing the project and specifying the basic approach to be used in its execution; segmenting the project into reasonable number of activities; estimating the time required to perform each activity; placing the activities in time order, considering both sequential and parallel performance

D.

Revising the schedule logic to make it possible to identify constraints of faulty logic; revising the durations in the n p schedule that have been based on assumptions regarding the \hay the work would be performed; revise the resources to work multiple shifts; evaluate the use of overtime