Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

AACE International Updated CCP Exam Questions and Answers by lloyd

Page: 9 / 13

AACE International CCP Exam Overview :

Exam Name: Certified Cost Professional (CCP) Exam
Exam Code: CCP Dumps
Vendor: AACE International Certification: AACE Certification
Questions: 189 Q&A's Shared By: lloyd
Question 36

In the application of the benefit/cost method of analysis, what are the criteria for determining whether a proposed project is acceptable?

Options:

A.

B/C is - 1.0

B.

B/C is <1.0

C.

B/C is > minimum ROR

D.

B/C is >1.0

Discussion
Question 37

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What class of estimate is used for the preliminary design phase of a project?

Options:

A.

Class 5 - order of magnitude estimate with +50% / -30% accuracy

B.

Class 1 - order of magnitude with +30% / -30% accuracy

C.

Class 4 - budget estimate with +30% / -15% accuracy

D.

Class 2 - definitive estimate with +15%/-5% accuracy

Discussion
Question 38

Which of the following best describes the three key participants for projects that are executed under a three-party contractual relationship?

Options:

A.

Contracting officer, contractor, and contractor project manager

B.

Procurement officer, underwriter, and project manager

C.

Owner, engineer, contractor

D.

Client, project manager, procurement manager

Discussion
Question 39

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

A cyclical process model was chosen as the basis for total cost management (TCM) because:

Options:

A.

It is one of the basic tenets of quality improvement

B.

Refinement is needed to prepare the estimate at completion (EAC)

C.

Strategic assets and projects have inherent life cycles

D.

It facilitates development of budgets and schedules

Discussion
Vienna
I highly recommend them. They are offering exact questions that we need to prepare our exam.
Jensen Jul 23, 2026
That's great. I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Melody
My experience with Cramkey was great! I was surprised to see that many of the questions in my exam appeared in the Cramkey dumps.
Colby Jul 16, 2026
Yes, In fact, I got a score of above 85%. And I attribute a lot of my success to Cramkey's dumps.
Teddie
yes, I passed my exam with wonderful score, Accurate and valid dumps.
Isla-Rose Jul 10, 2026
Absolutely! The questions in the dumps were almost identical to the ones that appeared in the actual exam. I was able to answer almost all of them correctly.
Norah
Cramkey is highly recommended.
Zayan Jul 25, 2026
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Page: 9 / 13

CCP
PDF

$36.75  $104.99

CCP Testing Engine

$43.75  $124.99

CCP PDF + Testing Engine

$57.75  $164.99