AACE International CCP Exam Overview :

Exam Name: Certified Cost Professional (CCP) Exam
Exam Code: CCP Dumps
Vendor: AACE International Certification: AACE
Questions: 189 Q&A's Shared By: madina
Question 8

An American company plans to acquire a new press machine from a Dutch manufacturer under the following conditions. One question remaining to be answered is the expected amount of capital recovery when salvage is accounted for.

Questions 8

The following question requites your selection of Scenario 1.4.150 from the tight side of your split screen. using the drop down menu, to reference during your response/choice o' responses

The present worth interest factor for this purchase in the fifth year would be:

Options:

A.

0.6209

B.

1.6474

C.

1.6105

D.

0.6070

Discussion
Inaya
Passed the exam. questions are valid. The customer support is top-notch. They were quick to respond to any questions I had and provided me with all the information I needed.
Cillian Jul 15, 2025
That's a big plus. I've used other dump providers in the past and the customer support was often lacking.
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh Jul 24, 2025
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
River
Hey, I used Cramkey Dumps to prepare for my recent exam and I passed it.
Lewis Jul 2, 2025
Yeah, I used these dumps too. And I have to say, I was really impressed with the results.
Ayra
How these dumps are necessary for passing the certification exam?
Damian Jul 11, 2025
They give you a competitive edge and help you prepare better.
Question 9

Deliberate low bidding is often referred to as buying the job. Which of the following would not be a reason for low bidding?

Options:

A.

Survival

B.

Backing out of the bid competition

C.

Reducing cm eliminating competition

D.

Detecting significant errors in the purchaser's request for quote

Discussion
Question 10

Meetings require:

Options:

A.

Goals, an agenda, preparation, relevant discussions, support for your actions and to consider the total physical and human setting of the meeting

B.

Goals, an agenda, preparation, conclusions, control and conversations that are relevant

C.

Goals, an agenda, preparation, control, good listening skills and relevant discussions

D.

Goals, an agenda, flipchart, computer projector, laser pointer and consulting with others where appropriate

Discussion
Question 11

Questions 11

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete. What is the current schedule performance index (SPI)?

Options:

A.

0.96

B.

0.88

C.

0.84

D.

1.14

Discussion