To help you prepare for the CCM FIDIC exam, we are offering free CCM FIDIC exam questions. All you need to do is sign up, provide your details, and prepare with the free CCM practice questions. Once you have done that, you will have access to the entire pool of Certified Contract Manager CCM test questions which will help you better prepare for the exam. Additionally, you can also find a range of Certified Contract Manager resources online to help you better understand the topics covered on the exam, such as Certified Contract Manager CCM video tutorials, blogs, study guides, and more. Additionally, you can also practice with realistic FIDIC CCM exam simulations and get feedback on your progress. Finally, you can also share your progress with friends and family and get encouragement and support from them.

Questions 2

For the FIDIC Red Book (both editions), the Contractor is required to submit a progress report monthly. When does the Contractor ' s reporting requirement end?

Options:

A.  

After issuance of the Taking-Over Certificate.

B.  

After issuance of the Performance Certificate.

C.  

At the Date of Completion of the Works (irrespective of whether there is minor outstanding work to be performed).

D.  

Until all outstanding works as stated in the Taking-Over Certificate are completed.

Discussion 0
Questions 3

(The Employer is a leading company in the hospital and medical care sector who wishes to build a new hospital. The Employer is considering approaching a financial institute to secure most of the funds; therefore, he requires clarity and stability in terms of the Project ' s budget and time for completion. Which book do you recommend?)

Options:

A.  

Red Book

B.  

Yellow Book

C.  

Silver Book

D.  

All the above

Discussion 0
Robin
Cramkey is highly recommended.
Jonah Jun 10, 2026
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh Jun 4, 2026
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Cody
I used Cramkey Dumps to prepare and a lot of the questions on the exam were exactly what I found in their study materials.
Eric Jun 16, 2026
Really? That's great to hear! I used Cramkey Dumps too and I had the same experience. The questions were almost identical.
Lennox
Something Special that they provide a comprehensive overview of the exam content. They cover all the important topics and concepts, so you can be confident that you are well-prepared for the test.
Aiza Jun 1, 2026
That makes sense. What makes Cramkey Dumps different from other study materials?
Questions 4

(Upon review of the revised programme, submitted by the Contractor, if the Engineer (under FIDIC Red or Yellow Books) or Employer (under FIDIC Silver Book) does not give a Notice of Non-Compliance within 14 days after receiving a revised programme, then… [complete the sentence, thereby considering FIDIC Red, Yellow, and Silver Books (edition 2017)]. (1 correct answer applies))

Options:

A.  

The Contractor shall submit a Notice to the Engineer or the Employer reminding him to give its approval on the revised programme.

B.  

The Engineer shall be deemed to have given a Consent and the revised programme shall be the Programme.

C.  

The Contractor cannot proceed in accordance with the Programme.

D.  

The Engineer is deemed to have no objection to use the revised Programme for the Works.

Discussion 0
Questions 5

Under the FIDIC Red and Yellow Books (edition 2017), which two of the following elements shall form part of the initial time Programme?

Options:

A.  

The date on which the right of access to and possession of (each part of) the Site is to be given to the Contractor.

B.  

The actual progress to date, any delay to such progress and the effects of such delay on other activities (if any).

C.  

The sequence and timing of the remedial work.

D.  

All key delivery dates of Plant and Materials.

Discussion 0