To help you prepare for the CCM FIDIC exam, we are offering free CCM FIDIC exam questions. All you need to do is sign up, provide your details, and prepare with the free CCM practice questions. Once you have done that, you will have access to the entire pool of Certified Contract Manager CCM test questions which will help you better prepare for the exam. Additionally, you can also find a range of Certified Contract Manager resources online to help you better understand the topics covered on the exam, such as Certified Contract Manager CCM video tutorials, blogs, study guides, and more. Additionally, you can also practice with realistic FIDIC CCM exam simulations and get feedback on your progress. Finally, you can also share your progress with friends and family and get encouragement and support from them.

Questions 2

For the FIDIC Red Book (both editions), the Contractor is required to submit a progress report monthly. When does the Contractor ' s reporting requirement end?

Options:

A.  

After issuance of the Taking-Over Certificate.

B.  

After issuance of the Performance Certificate.

C.  

At the Date of Completion of the Works (irrespective of whether there is minor outstanding work to be performed).

D.  

Until all outstanding works as stated in the Taking-Over Certificate are completed.

Discussion 0
Miriam
Highly recommended Dumps. 100% authentic and reliable. Passed my exam with wonderful score.
Milan Sep 19, 2026
I see. Thanks for the information. I'll definitely keep Cramkey in mind for my next exam.
Madeleine
Passed my exam with my dream score…. Guys do give these dumps a try. They are authentic.
Ziggy Sep 26, 2026
That's really impressive. I think I might give Cramkey Dumps a try for my next certification exam.
Walter
Yayyy!!! I passed my exam with the help of Cramkey Dumps. Highly appreciated!!!!
Angus Sep 16, 2026
YES….. I saw the same questions in the exam.
Georgina
I used Cramkey Dumps to prepare for my recent exam and I have to say, they were a huge help.
Corey Sep 9, 2026
Really? How did they help you? I know these are the same questions appears in exam. I will give my try. But tell me if they also help in some training?
Josie
I just passed my certification exam using their dumps and I must say, I was thoroughly impressed.
Fatimah Sep 9, 2026
You’re right. The dumps were authentic and covered all the important topics. I felt confident going into the exam and it paid off.
Questions 3

(The Employer is a leading company in the hospital and medical care sector who wishes to build a new hospital. The Employer is considering approaching a financial institute to secure most of the funds; therefore, he requires clarity and stability in terms of the Project ' s budget and time for completion. Which book do you recommend?)

Options:

A.  

Red Book

B.  

Yellow Book

C.  

Silver Book

D.  

All the above

Discussion 0
Questions 4

(Upon review of the revised programme, submitted by the Contractor, if the Engineer (under FIDIC Red or Yellow Books) or Employer (under FIDIC Silver Book) does not give a Notice of Non-Compliance within 14 days after receiving a revised programme, then… [complete the sentence, thereby considering FIDIC Red, Yellow, and Silver Books (edition 2017)]. (1 correct answer applies))

Options:

A.  

The Contractor shall submit a Notice to the Engineer or the Employer reminding him to give its approval on the revised programme.

B.  

The Engineer shall be deemed to have given a Consent and the revised programme shall be the Programme.

C.  

The Contractor cannot proceed in accordance with the Programme.

D.  

The Engineer is deemed to have no objection to use the revised Programme for the Works.

Discussion 0
Questions 5

Under the FIDIC Red and Yellow Books (edition 2017), which two of the following elements shall form part of the initial time Programme?

Options:

A.  

The date on which the right of access to and possession of (each part of) the Site is to be given to the Contractor.

B.  

The actual progress to date, any delay to such progress and the effects of such delay on other activities (if any).

C.  

The sequence and timing of the remedial work.

D.  

All key delivery dates of Plant and Materials.