Pre-Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

SAP Updated C_TS422_2020 Exam Questions and Answers by cruz

Page: 2 / 5

SAP C_TS422_2020 Exam Overview :

Exam Name: SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing
Exam Code: C_TS422_2020 Dumps
Vendor: SAP Certification: SAP Certified Application Associate
Questions: 148 Q&A's Shared By: cruz
Question 8

What are some uses for the low-level code assigned to each material? Note: There are 2 correct answers to this question.

Options:

A.

It is used in MRP to determine the sequence in which materials are planned.

B.

It is used by engineering to identify sub items in an engineering bill of material(BOM).

C.

It is used by product costing to determine how costs are rolled up.

D.

It is used by ATP to determine the priority of alternative components.

Discussion
Question 9

What determines whether the planned independent requirements in MRP consume other requirements?

Options:

A.

Requirements type

B.

Order type

C.

Requirements profile

D.

Consumption sequence procedure

Discussion
Miley
Hey, I tried Cramkey Dumps for my IT certification exam. They are really awesome and helped me pass my exam with wonderful score.
Megan Mar 4, 2026
That’s great!!! I’ll definitely give it a try. Thanks!!!
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Mar 13, 2026
Thanks for the recommendation! I'll check it out.
River
Hey, I used Cramkey Dumps to prepare for my recent exam and I passed it.
Lewis Mar 10, 2026
Yeah, I used these dumps too. And I have to say, I was really impressed with the results.
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Mar 14, 2026
Yeah, definitely. I experienced the same.
Question 10

Which task list types can have parallel sequences? There are 2 correct answers to this question.

Options:

A.

Routings (N)

B.

Master recipes (2)

C.

Rate routings (R)

D.

Reference operation sets (S)

Discussion
Question 11

What does it mean for the production planner when MRP works with infinite capacities?

Options:

A.

MRP assigns capacity requirements automatically to work center is with the earliest available capacity.

B.

MRP creates capacity requirements without checking the capacity of a work center.

C.

MRP creates capacity requirements only if the work center has sufficient capacity.

D.

MRP assigns capacity requirements automatically after the last scheduled order on a work center.

Discussion
Page: 2 / 5

C_TS422_2020
PDF

$36.75  $104.99

C_TS422_2020 Testing Engine

$43.75  $124.99

C_TS422_2020 PDF + Testing Engine

$57.75  $164.99