Question 20

Which of the following statements is NOT TRUE?

Options:

A.

The SRO is accountable for confirming Programme Mandate.

B.

The SRO is accountable for the Programme Brief.

C.

The Programme Manager is responsible for the Vision Statement.

D.

The Programme Manager is responsible for the Blueprint.

Discussion
Aryan
Absolutely rocked! They are an excellent investment for anyone who wants to pass the exam on the first try. They save you time and effort by providing a comprehensive overview of the exam content, and they give you a competitive edge by giving you access to the latest information. So, I definitely recommend them to new students.
Jessie May 31, 2026
did you use PDF or Engine? Which one is most useful?
Georgina
I used Cramkey Dumps to prepare for my recent exam and I have to say, they were a huge help.
Corey Jun 3, 2026
Really? How did they help you? I know these are the same questions appears in exam. I will give my try. But tell me if they also help in some training?
Anya
I must say they're considered the best dumps available and the questions are very similar to what you'll see in the actual exam. Recommended!!!
Cassius Jun 14, 2026
Yes, they offer a 100% success guarantee. And many students who have used them have reported passing their exams with flying colors.
Anaya
I found so many of the same questions on the real exam that I had already seen in the Cramkey Dumps. Thank you so much for making exam so easy for me. I passed it successfully!!!
Nina Jun 4, 2026
It's true! I felt so much more confident going into the exam because I had already seen and understood the questions.
Question 21

Which of following best defines Outcomes?

Options:

A.

Deliverable of a project

B.

Completed set of project outputs

C.

Measurable improvement resulting from outcomes perceived as advantage

D.

New operational state achieved after transition of capability in live operations

Discussion
Question 22

The programme is in the ‘design the outcomes’ process for the first time. The Research and Development Project team has recommended that UU sources an imported next generation smart meter. This is an alternative to the development of the smart meter internally. The imported meter can be fully implemented before the CEO retires in three years' time. However, there is a possibility that this meter could lead to future information security risks.

Is this recommendation an appropriate application of the ‘decisions' theme, and why?

Options:

A.

Yes, because the proposed option should gain the CEO’s full support

B.

Yes, because providing a clear recommendation should bring pace and value

C.

No, because there are security risks identified with the option proposed

D.

No, because a ‘do-nothing’ option and at least two others should be provided

Discussion
Question 23

The programme is in the middle of Tranche 2. A new SRO has been appointed. To understand the current status of the programme, the SRO has asked for a health check to be carried out. The programme office lead has recruited an external consultant to carry out the health check.

Which assurance success factor does this demonstrate?

Options:

A.

Independence

B.

Accountability

C.

Coordination

D.

Risk appetite

Discussion