Question 12

Test objectives for systems testing of a safety critical system include completion of all outstanding defect correction. Regression testing is required following defect correction at all test levels. Which TWO of the following metrics would be MOST suitable for determining whether the test objective has been met? [K2]

a. Regression tests run and passed in systems testing

b. Incidents closed in systems testing

c. Planned tests run and passed in system testing

d. Planned tests run and passed at all levels of testing

e. Incidents raised and closed at all levels of testing

Options:

A.

a and e

B.

b and c

C.

d and e

D.

a and b

Discussion
Billy
It was like deja vu! I was confident going into the exam because I had already seen those questions before.
Vincent Jun 22, 2026
Definitely. And the best part is, I passed! I feel like all that hard work and preparation paid off. Cramkey is the best resource for all students!!!
Esmae
I highly recommend Cramkey Dumps to anyone preparing for the certification exam.
Mollie Jun 25, 2026
Absolutely. They really make it easier to study and retain all the important information. I'm so glad I found Cramkey Dumps.
Addison
Want to tell everybody through this platform that I passed my exam with excellent score. All credit goes to Cramkey Exam Dumps.
Libby Jun 21, 2026
That's good to know. I might check it out for my next IT certification exam. Thanks for the info.
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson Jun 12, 2026
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Lennie
I passed my exam and achieved wonderful score, I highly recommend it.
Emelia Jun 15, 2026
I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Question 13

Which of the main activities of the fundamental test process does the task ‘verify the test environment set up is correct’ relate to? [K1]

Options:

A.

Planning and control

B.

Analysis and design

C.

Implementation and execution

D.

Evaluating exit criteria and reporting

Discussion
Question 14

Which of the following test case design techniques is white box (structure-based)? [K1]

Options:

A.

Use case testing

B.

State transition testing

C.

Decision testing

D.

Equivalence partitioning

Discussion
Question 15

Which of the following is a white box testing design characteristic?

Options:

A.

To be based on specifications

B.

To be based on an analysis of the test basis documentation

C.

To be based on an analysis of the structure of the component or system

D.

To include both functional and non-functional testing

Discussion
Page: 3 / 27
Title
Questions
Posted

CTFL_Syll2018
PDF

$36.75  $104.99

CTFL_Syll2018 Testing Engine

$43.75  $124.99

CTFL_Syll2018 PDF + Testing Engine

$57.75  $164.99