Question 52

During which PI planning activity are Stories written and sequenced?

Options:

A.

The team breakout session

B.

The draft plan review

C.

The management Review and Problem-Solving workshop

D.

The business context presentation

Discussion
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Aug 9, 2025
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Madeleine
Passed my exam with my dream score…. Guys do give these dumps a try. They are authentic.
Ziggy Aug 8, 2025
That's really impressive. I think I might give Cramkey Dumps a try for my next certification exam.
Robin
Cramkey is highly recommended.
Jonah Aug 5, 2025
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Carson
Yeah, definitely. I would definitely recommend Cramkey Dumps to anyone who is preparing for an exam.
Rufus Aug 16, 2025
Me too. They're a lifesaver!
Ivan
I tried these dumps for my recent certification exam and I found it pretty helpful.
Elis Aug 10, 2025
Agree!!! The questions in the dumps were quite similar to what came up in the actual exam. It gave me a good idea of the types of questions to expect and helped me revise efficiently.
Question 53

Quality is first and foremost a function of what in a Lean-Agile concept?

Options:

A.

Preserving options

B.

Culture of shared responsibility

C.

Empowered Solution authority

D.

Deployment on demand

Discussion
Question 54

The analyzing step of the Portfolio Kanban system has a new Epic with a completed Lean business case. What best describes the next step for the Epic?

Options:

A.

It will be implemented once the Epic Owner approves the Lean business case.

B.

It will be moved to the ready state in the Portfolio Kanban if it receives a 'go' decision from Lean Portfolio Management.

C.

It will remain in the analyzing step until one or more Agile Release Trains have the capacity to implement it.

D.

It will be implemented if it has the highest weighted shortest job first (WSJF) ranking

Discussion
Question 55

What does the "C" represent in the CALMR approach to DevOps?

Options:

A.

Completion

B.

Cycle-time

C.

Culture

D.

Continuous Integration

Discussion
Page: 13 / 19
Title
Questions
Posted

SP-SAFe-Practitioner
PDF

$42  $104.99

SP-SAFe-Practitioner Testing Engine

$50  $124.99

SP-SAFe-Practitioner PDF + Testing Engine

$66  $164.99