Question 52

Which of the following is the MOST important benefit of implementing a contract management system?

Options:

A.

Greater visibility for reverse auctions

B.

Lower legal staff costs

C.

Access to a cooperative purchasing group

D.

Higher value-added activities

Discussion
Andrew
Are these dumps helpful?
Jeremiah Oct 2, 2025
Yes, Don’t worry!!! I'm confident you'll find them to be just as helpful as I did. Good luck with your exam!
Faye
Yayyyy. I passed my exam. I think all students give these dumps a try.
Emmeline Oct 18, 2025
Definitely! I have no doubt new students will find them to be just as helpful as I did.
Vienna
I highly recommend them. They are offering exact questions that we need to prepare our exam.
Jensen Oct 11, 2025
That's great. I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Ace
No problem! I highly recommend Cramkey Dumps to anyone looking to pass their certification exams. They will help you feel confident and prepared on exam day. Good luck!
Harris Oct 28, 2025
That sounds amazing. I'll definitely check them out. Thanks for the recommendation!
Question 53

A chemical company develops a new product that relies heavily on quartz, a common and abundant mineral. The company believes that the new product is critical to its financial success and future

growth. In developing a sourcing strategy for quartz, the company supply manager should focus PRIMARILY on

Options:

A.

ensuring long-term availability of supply

B.

reducing exposure to price increases or supply disruption

C.

using volume and economies of scale to minimize price

D.

streamlining the supply management process to achieve efficiency

Discussion
Question 54

PQR’s supply manager signs a contract with Supplier X for delivery of parts totaling $1,250,000 per year for four years. Accompanying the contract is a copy of the organization’s signing policy, which states that supply managers have authority to execute contracts up to $1,000,000 per year. Supplier X questions the discrepancy, but is told verbally by the supply manager that the policy has changed, and supply managers now have a $1,500,000 per year signing limit for up to five years.

Senior management at PQR discovers the supply manager's misstatement and tries to disavow the contract. This attempt will likely be

Options:

A.

successful, as the supplier should have respected the written signing policy

B.

unsuccessful, because the supply manager's verbal statement represents a binding agreement

C.

unsuccessful, as the supply manager's status and statement constitute apparent authority

D.

successful, provided the disavowal occurs within three business days of contract signing

Discussion
Question 55

Parts characterized by high cost/value and low technical complexity are categorized as

Options:

A.

specialized

B.

custom

C.

off-the-shelf

D.

standardized

Discussion