Comprehensive and Detailed Explanation From Exact Extract (CSI-Based)
According to the Construction Specifications Institute (CSI) and CDT exam content, the General Conditions of the Contract form the foundational “baseline” set of administrative, procedural, and legal requirements for every construction contract. All other contracting documents—including Supplementary Conditions, Division 01, and specification sections—are modified in relation to this baseline.
Why the Correct Answer Is General Conditions (Option D)
CSI practice guides describe the General Conditions as:
The standard baseline document for project relationships, responsibilities, rights, and procedures.
The “default” set of requirements unless modified by Supplementary Conditions or Division 01.
The document against which all deviations must be clearly identified, especially when supplementary or project-specific requirements alter the standard conditions.
General Conditions define or baseline:
Roles and responsibilities of owner, contractor, A/E
Contract time, payments, changes, submittals, inspections
Dispute resolution
Site conditions, insurance, and protection of work
CSI emphasizes that the General Conditions do not change for each project unless Supplementary Conditions modify them, which reinforces that they form the baseline.
Why the Other Options Are Incorrect
A. General Requirements (Division 01)
Division 01 sections coordinate the administrative and procedural requirements for the project, but they expand upon or modify the General Conditions—not the other way around. They cannot be the baseline because they themselves rely on the baseline established in the General Conditions.
B. Supplementary Conditions
These modify the General Conditions to address project-specific legal or regulatory requirements (e.g., bonding, liquidated damages, insurance). They create deviations, not the baseline from which deviations are identified.
C. Project Manual
The Project Manual is a collection of documents—including bidding requirements, contract forms, General Conditions, Supplementary Conditions, and specifications. It is not itself the baseline; it contains the baseline (the General Conditions).
Key CSI References
CSI Project Delivery Practice Guide – Chapters on Procurement and Contracting, discussing General Conditions as the base document for rights, responsibilities, and procedures.
CSI Construction Specifications Practice Guide – Sections on Contract Documents hierarchy and coordination.