In CSI’s project delivery framework, the preconstruction meeting (often called the preconstruction conference) is a formal meeting held after award of the construction contract and before substantial field work begins. Its typical purposes match the stem of this question almost word-for-word:
Introduce the key members of the owner’s team, the design team, and the contractor’s team.
Review and establish communication protocols – who communicates with whom, in what format (letters, emails, RFIs, submittals), and through which channels (e.g., via the A/E as the owner’s representative).
Explain administrative procedures for submittals, RFIs, change orders, applications for payment, project meetings, record documents, and closeout requirements.
Clarify roles and responsibilities, lines of authority, and decision-making processes during construction.
Review the project schedule, major milestones, site logistics, and constraints so everyone begins the project with a common understanding.
These points are fully consistent with how CSI’s Project Delivery Practice Guide and typical Division 01 “Project Management and Coordination” sections describe the preconstruction conference: as the kickoff meeting for the construction phase, focused on communication, procedures, and administration—not bidding or detailed technical coordination.
Why the other options are not correct:
A. Mobilization meeting“Mobilization” refers to the contractor’s process of moving onto the site (bringing in equipment, setting up field offices, etc.). While a project might have discussions about mobilization, “mobilization meeting” is not the standard CSI project-delivery term for this formal kickoff. The structured, procedure-focused meeting described in the question is the preconstruction meeting.
C. Prebid meetingA prebid meeting (pre-bid conference) occurs during procurement, before bids are submitted. Its primary purposes are to familiarize prospective bidders with the project, review procurement requirements, visit the site, and answer questions that might affect bids. It does not introduce the already-selected construction team, nor does it establish the project’s communication and administrative procedures for contract execution. That occurs after award in the preconstruction meeting.
D. Coordination meetingCoordination meetings are typically recurring, working meetings during construction to resolve ongoing technical, scheduling, or coordination issues between trades (e.g., MEP coordination). They do not serve as the initial, formal kickoff to introduce teams and set overall administrative and communication “ground rules.”
Therefore, the meeting that introduces the design and construction teams, sets communication ground rules, and explains administrative processes is the Preconstruction meeting (Option B), as aligned with CSI project delivery and Division 01 practices.
Key CSI References (titles only, no links):
CSI Project Delivery Practice Guide – chapters on Construction Phase and Project Meetings (Preconstruction Conference).
CSI Construction Specifications Practice Guide – discussions of Division 01 “Project Management and Coordination” and required project meetings.
CSI CDT Body of Knowledge – topic area: “Construction Phase Services and Communication.”