Question 24

The Head Landscape Gardener liaised with several key stakeholders before changing the direction of the pathway around the grounds to ensure all of the new features in

the gardens could be enjoyed.

Which Agile principle MOST influences this course of action?

Options:

A.

Focus on the business need.

B.

Deliver on time.

C.

Collaborate.

D.

Never compromise quality.

Discussion
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey May 16, 2026
Yeah, definitely. I experienced the same.
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella May 2, 2026
That's great. I think I'll give Cramkey Dumps a try.
Erik
Hey, I have passed my exam using Cramkey Dumps?
Freyja May 9, 2026
Really, what are they? All come in your pool? Please give me more details, I am going to have access their subscription. Please brother, give me more details.
Nadia
Why these dumps are important? Can I pass my exam without these dumps?
Julian May 22, 2026
The questions in the Cramkey dumps are explained in detail and there are also study notes and reference materials provided. This made it easier for me to understand the concepts and retain the information better.
Question 25

Which 2 statements explain why the Contract Architect would be an appropriate Technical Co-ordinator?

Options:

A.

Is an external consultant.

B.

Has good leadership skills.

C.

Has experience of working with the company previously.

D.

Has a good, technical understanding of the work of the other professionals engaged in the project.

E.

Is an authority on local planning applications.

Discussion
Question 26

Column 1 is a list of actions taken within the project. For each action in Column 1, select from Column 2 the iterative development activity that the action represents. Each selection from Column 2 can be used once, more than once or not at all.

Column 1:

1. The Solution Development Team cleared and prepared the area, ready for the bar infrastructure to be installed.

2. The Gardener decided the order in which the flowers would be planted in the borders and jotted it down in a notebook.

3. Before the Solution Development Team built the infrastructure for the bar area, the Architect pointed out what was required.

4. The Architect checked with the decorators that tasks had been completed to a satisfactory standard, and agreed a list of items that needed further coats of paint or cleaning up.

5. The Gardener began planting the borders and has placed an order for further bulbs to complete this task.

Column 2:

A) Thought

B) Action

C) Conversation

Questions 26

Options:

Discussion
Question 27

How should the Project Manager encourage the contractors to turn up on time?

Options:

A.

Place a penalty clause on all contractors for late arrival.

B.

Appoint Team Leaders to each of the electrical and plumbing teams.

C.

Encourage open and honest communication to re-establish an environment of trust.

D.

Hold a separate Daily Stand-up meeting early in the morning, for the contractors only.

Discussion