Question 32

Brinda Vyas and Mira Bachar have agreed to use content from a marketing brochure to describe guest-centric Product Goals for the Eco-Spa. These goals describe specific treatments that the Spa might offer and will be used to identify prioritizable Product Backlog items that could contribute to that treatment. One such Product Goal is described as:

Hydrotherapy in Mineral-Rich Spring Pools

Immerse yourself in mineral-rich hydrotherapy pools designed to soothe muscies, improve circulation, and promote

deep relaxation. Experience the gentle power of temperature-controlled waters and therapeutic massage jets in a lush

and tranquil tropical garden setting and let nature ' s healing embrace rejuvenate both your body and your mind.

In addition to the Developers, the teams include:

Questions 32

(Which of the following actions is appropriate when defining prioritizable Product Backlog items for the ' Hydrotherapy in Mineral-Rich Spring Pools ' Product Goal?)

Options:

A.

Break the Product Goal into smaller Backlog items, each justified by the value it contributes to the hydrotherapy experience described.

B.

Create a Backlog item for every infrastructure need to ensure nothing is missed from the range of features to be prioritized.

C.

Use MoSCoW to prioritize Product Backlog items based on technical feasibility and cost of delivery each feature described.

D.

Defer the prioritization of Product Backlog items until Sprint Planning so that the Delivery Teams can decide what is achievable at that time.

Discussion
Question 33

(There were several responses to Brinda Vyas ' suggestion of a tranquil garden for guided meditation. While all valid and valuable, which opinion does NOT align with AgilePM responsibilities?)

Options:

A.

Brinda Vyas emphasized the garden ' s strategic importance in enhancing guest experience and meeting business goals.

B.

Brinda Vyas linked the garden to the resort ' s long-term objectives and the project ' s business case.

C.

Sukra Aroon considered technical feasibility and identified risks in infrastructure requirements.

D.

Sukra Aroon dismissed the garden rationale, saying guided meditation could happen in a treatment room.

E.

Mira Bachar prioritized the garden against other deliverables, ensuring alignment with stakeholder needs and project goals.

F.

Mira Bachar clarified the Product Goals for the Delivery Teams to deliver to contribute to the overall solution.

G.

A local expert shared how the garden ' s design could enhance meditation experiences for guest in line with well-being principles.

Discussion
Question 34

During the Foundations phase for Project Increment 4, Sukra Aroon held a meeting with Hira, Mira Bachar, andWanida Anong, to ensure alignment and compliance with EPR company policies, local regulations, and international standards. The meeting also clarified how financial and investment decisions would be made for Project Increment 4, ensuring alignment with EPR business priorities, and how this information will be tracked,

controlled and evidenced.

Wanida Anong, who works across multiple sites worldwide, attended the meeting in person but has limited availability throughout the Project Increment.

Questions 34

(On receiving the meeting invitation, Hira responded suggesting that Brinda Vyas should also be invited to the meeting. Based on AgilePM guidance, which of the following does NOT present an appropriate justification for Brinda Vyas ' attendance?)

Options:

A.

Brinda Vyas is responsible for ensuring that the solution aligns with the strategic direction of the business and provides the expected value. Her input will help shape decisions related to capital investment.

B.

Brinda Vyas is accountable for the financial and regulatory governance aspects of the project and must personally oversee compliance-related discussions to ensure standards for these are met.

C.

Brinda Vyas plays a key role in confirming that the regulatory and quality expectations being discussed are aligned with the business need and will not undermine the viability of the project.

D.

The understanding of regulatory compliance needs for the Eco-spa gained by attending the meeting will help Brinda Vyas keep business stakeholders aligned with the business solution as it emerges.

Discussion
Lois
I passed my exam with wonderful score. Their dumps are 100% valid and I felt confident during the exam.
Ernie Mar 28, 2026
Absolutely. The best part is, the answers in the dumps were correct. So, I felt confident and well-prepared for the exam.
Everleigh
I must say that they are updated regularly to reflect the latest exam content, so you can be sure that you are getting the most accurate information. Plus, they are easy to use and understand, so even new students can benefit from them.
Huxley Mar 27, 2026
That's great to know. So, you think new students should buy these dumps?
Nylah
I've been looking for good study material for my upcoming certification exam. Need help.
Dolly Mar 21, 2026
Then you should definitely give Cramkey Dumps a try. They have a huge database of questions and answers, making it easy to study and prepare for the exam. And the best part is, you can be sure the information is accurate and relevant.
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony Mar 7, 2026
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Kingsley
Do anyone guide my how these dumps would be helpful for new students like me?
Haris Mar 23, 2026
Absolutely! They are highly recommended for anyone looking to pass their certification exam. The dumps are easy to understand and follow, making it easier for you to study and retain the information.
Question 35

Brinda Vyas and Mira Bachar have agreed to use content from a marketing brochure to describe guest-centric Product Goals for the Eco-Spa. These goals describe specific treatments that the Spa might offer and will be used to identify prioritizable Product Backlog items that could contribute to that treatment. One such Product Goal is described as:

Hydrotherapy in Mineral-Rich Spring Pools

Immerse yourself in mineral-rich hydrotherapy pools designed to soothe muscies, improve circulation, and promote

deep relaxation. Experience the gentle power of temperature-controlled waters and therapeutic massage jets in a lush

and tranquil tropical garden setting and let nature ' s healing embrace rejuvenate both your body and your mind.

In addition to the Developers, the teams include:

Questions 35

(Which one of the following actions will ensure that Product Backlog items for the Hydrotherapy infrastructure remain aligned with the planned treatment experience throughout development?)

Options:

A.

The Infrastructure Team should regularly review and refine Backlog items with Mira Bachar to maintain alignment.

B.

Lock all Backlog items after initial prioritization to prevent scope change and allow the Infrastructure Team to focus on delivering them.

C.

Frequently reassess the priority of Product Backlog items to ensure the Infrastructure Team remain focused on the highest value features.

D.

Encourage the Infrastructure Team to prioritize features for the hydrotherapy treatments since they understand what can be achieved within each Sprint.