Question 168

In a lean environment, the batch-size decision for planning "A" items would be done by:

Options:

A.

least total cost.

B.

min-max system.

C.

lot-for-lot (L4L).

D.

periodic order quantity.

Discussion
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony Jan 5, 2026
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Sarah
Yeah, I was so relieved when I saw that the question appeared in the exam were similar to their exam dumps. It made the exam a lot easier and I felt confident going into it.
Aaliyah Jan 20, 2026
Same here. I've heard mixed reviews about using exam dumps, but for us, it definitely paid off.
Lois
I passed my exam with wonderful score. Their dumps are 100% valid and I felt confident during the exam.
Ernie Jan 7, 2026
Absolutely. The best part is, the answers in the dumps were correct. So, I felt confident and well-prepared for the exam.
Mylo
Excellent dumps with authentic information… I passed my exam with brilliant score.
Dominik Jan 1, 2026
That's amazing! I've been looking for good study material that will help me prepare for my upcoming certification exam. Now, I will try it.
Question 169

An organization has decided to advance from qualitative risk assessment to quantitative risk analysis. The information security risk analyst has been tasked with replacing the organization’s qualitative likelihood scale of low, medium, and high with a quantitative approach. Which is the BEST approach for replacing the qualitative input values?

Options:

A.

Estimate the probability of the scenario ever occurring and use that percentage.

B.

Replace the qualitative scale’s thresholds with point percentages (e.g., low = 25%; medium = 50%; high = 75%) and use those percentages.

C.

Replace the qualitative scale’s thresholds with ranges of percentages (e.g., low = 1–33%; medium = 34–66%; high = 67–99%) and use those percentages.

D.

Estimate the probability of the scenario occurring within the following year and use that percentage.

Discussion
Question 170

While conducting penetration testing, one of the testers noticed evidence of additional penetration activities not part of the test. Which of the following is the NEXT course of action for the lead penetration tester?

Options:

A.

Continue testing and report the event at the end of the day.

B.

Stop testing and monitor activity.

C.

Stop testing and report the event.

D.

Complete the test and report the event at the end of the test.

Discussion
Question 171

A security engineer needs to perform threat modeling on a microprocessor design for an Internet of Things (IoT) application. Using the MITRE Common Weakness Enumeration (CWE) catalog for hardware, a risk analysis is performed. What kind of threat modeling approach would be BEST to identify entry points into the system based on motivation?

Options:

A.

System centric

B.

Attacker centric

C.

Threat centric

D.

Asset centric

Discussion
Page: 42 / 43
Title
Questions
Posted

CPIM-8.0
PDF

$42  $104.99

CPIM-8.0 Testing Engine

$50  $124.99

CPIM-8.0 PDF + Testing Engine

$66  $164.99