Question 16

The Commissioning Authority (CxA) must report results, findings and recommendations directly to the

Options:

A.

owner

B.

architect

C.

contractor

D.

project manager

Discussion
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella Aug 25, 2024
That's great. I think I'll give Cramkey Dumps a try.
Nadia
Why these dumps are important? Can I pass my exam without these dumps?
Julian Oct 22, 2024
The questions in the Cramkey dumps are explained in detail and there are also study notes and reference materials provided. This made it easier for me to understand the concepts and retain the information better.
Esmae
I highly recommend Cramkey Dumps to anyone preparing for the certification exam.
Mollie Aug 15, 2024
Absolutely. They really make it easier to study and retain all the important information. I'm so glad I found Cramkey Dumps.
Cecilia
Yes, I passed my certification exam using Cramkey Dumps.
Helena Sep 19, 2024
Great. Yes they are really effective
Question 17

Regarding the Materials and Resources Credit, Building Product Disclosure and Optimization - Sourcing of Raw Materials, Option 2. Leadership Extraction Practices, in addition to materials costs, what information is needed to determine the total cost of each product?

Options:

A.

Taxes and delivery costs

B.

Taxes and installation costs

C.

Installation equipment and labor

D.

Transportation costs and installation labor

Discussion
Question 18

A project has performed an energy model which has resulted in the following energy end use consumption:

Questions 18

To meet the requirements for Energy and Atmosphere Credit, Advanced Energy Metering, Option 2. Advanced Metering, energy meters must be installed for energy end uses in

Options:

A.

space cooling, interior fans and receptacles

B.

interior lighting, space heating, space cooling and interior fans

C.

interior lighting, space heating, space cooling, interior fans and receptacles

D.

exterior lighting, interior lighting, space heating, space cooling, interior fans, service water heating and receptacles

Discussion
Question 19

In addition to the basic requirements for Energy and Atmosphere, Fundamental Commissioning and Verification, which is required to achieve Energy and Atmosphere, Enhanced Commissioning, Option 1?

Options:

A.

Develop and implement a commissioning plan

B.

Review the contractor's submittals for compliance with design documents

C.

Verify the installation and performance of the systems being commissioned

D.

Review the owner's requirements and the basis of design for clarity and completeness