Question 16

The Commissioning Authority (CxA) must report results, findings and recommendations directly to the

Options:

A.

owner

B.

architect

C.

contractor

D.

project manager

Discussion
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Jan 26, 2026
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Jan 24, 2026
Yeah, definitely. I experienced the same.
Alaya
Best Dumps among other dumps providers. I like it so much because of their authenticity.
Kaiden Jan 23, 2026
That's great. I've used other dump providers in the past and they were often outdated or had incorrect information. This time I will try it.
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony Jan 5, 2026
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Inaaya
Are these Dumps worth buying?
Fraser Jan 15, 2026
Yes, of course, they are necessary to pass the exam. They give you an insight into the types of questions that could come up and help you prepare effectively.
Question 17

Regarding the Materials and Resources Credit, Building Product Disclosure and Optimization - Sourcing of Raw Materials, Option 2. Leadership Extraction Practices, in addition to materials costs, what information is needed to determine the total cost of each product?

Options:

A.

Taxes and delivery costs

B.

Taxes and installation costs

C.

Installation equipment and labor

D.

Transportation costs and installation labor

Discussion
Question 18

A project has performed an energy model which has resulted in the following energy end use consumption:

Questions 18

To meet the requirements for Energy and Atmosphere Credit, Advanced Energy Metering, Option 2. Advanced Metering, energy meters must be installed for energy end uses in

Options:

A.

space cooling, interior fans and receptacles

B.

interior lighting, space heating, space cooling and interior fans

C.

interior lighting, space heating, space cooling, interior fans and receptacles

D.

exterior lighting, interior lighting, space heating, space cooling, interior fans, service water heating and receptacles

Discussion
Question 19

In addition to the basic requirements for Energy and Atmosphere, Fundamental Commissioning and Verification, which is required to achieve Energy and Atmosphere, Enhanced Commissioning, Option 1?

Options:

A.

Develop and implement a commissioning plan

B.

Review the contractor's submittals for compliance with design documents

C.

Verify the installation and performance of the systems being commissioned

D.

Review the owner's requirements and the basis of design for clarity and completeness

Discussion