Question 16

The Commissioning Authority (CxA) must report results, findings and recommendations directly to the

Options:

A.

owner

B.

architect

C.

contractor

D.

project manager

Discussion
Nia
Why are these Dumps so important for students these days?
Mary Dec 19, 2025
With the constantly changing technology and advancements in the industry, it's important for students to have access to accurate and valid study material. Cramkey Dumps provide just that. They are constantly updated to reflect the latest changes and ensure that the information is up-to-date.
Teddie
yes, I passed my exam with wonderful score, Accurate and valid dumps.
Isla-Rose Dec 3, 2025
Absolutely! The questions in the dumps were almost identical to the ones that appeared in the actual exam. I was able to answer almost all of them correctly.
Andrew
Are these dumps helpful?
Jeremiah Dec 22, 2025
Yes, Don’t worry!!! I'm confident you'll find them to be just as helpful as I did. Good luck with your exam!
Wyatt
Passed my exam… Thank you so much for your excellent Exam Dumps.
Arjun Dec 21, 2025
That sounds really useful. I'll definitely check it out.
Honey
I highly recommend it. They made a big difference for me and I'm sure they'll help you too. Just make sure to use them wisely and not solely rely on them. They should be used as a supplement to your regular studies.
Antoni Dec 10, 2025
Good point. Thanks for the advice. I'll definitely keep that in mind.
Question 17

Regarding the Materials and Resources Credit, Building Product Disclosure and Optimization - Sourcing of Raw Materials, Option 2. Leadership Extraction Practices, in addition to materials costs, what information is needed to determine the total cost of each product?

Options:

A.

Taxes and delivery costs

B.

Taxes and installation costs

C.

Installation equipment and labor

D.

Transportation costs and installation labor

Discussion
Question 18

A project has performed an energy model which has resulted in the following energy end use consumption:

Questions 18

To meet the requirements for Energy and Atmosphere Credit, Advanced Energy Metering, Option 2. Advanced Metering, energy meters must be installed for energy end uses in

Options:

A.

space cooling, interior fans and receptacles

B.

interior lighting, space heating, space cooling and interior fans

C.

interior lighting, space heating, space cooling, interior fans and receptacles

D.

exterior lighting, interior lighting, space heating, space cooling, interior fans, service water heating and receptacles

Discussion
Question 19

In addition to the basic requirements for Energy and Atmosphere, Fundamental Commissioning and Verification, which is required to achieve Energy and Atmosphere, Enhanced Commissioning, Option 1?

Options:

A.

Develop and implement a commissioning plan

B.

Review the contractor's submittals for compliance with design documents

C.

Verify the installation and performance of the systems being commissioned

D.

Review the owner's requirements and the basis of design for clarity and completeness

Discussion