Question 36

Scenario

Please read this scenario prior to answering the Question

You are serving as an Enterprise Architect at a large aerospace company. It designs, manufactures and sells civil and military aviation products worldwide and manufactures in multiple countries both inside and outside of the European Union. The company has grown rapidly by acquisition and has inherited numerous different procurement processes and related IT systems.

Recently, several procurement processes, within the civil aviation business, have has problems related to the timing of purchases, which has led to excess inventory. The Vice President in charge of Supply Chain Management has made the decision to consolidate and reduce redundant procurement processes and systems. He has committed to the CEO that the business will move to a " Just-in-time " procurement system so as to keep inventory costs low.

The TOGAF standard is used for internal Enterprise Architecture activities. At present, there are no architectural assets in the Architecture Repository related to this initiative. All assets will need to be acquired, customized, or created from scratch. The company prefers to implement commercial off the shelf package applications with little customization. The CIO, who is the project sponsor, has stated that she is not concerned about preserving the existing procurement processes or systems.

This project is using an iterative approach for executing the Architecture Development Method (ADM). The architecture development project has completed the Architecture Vision Phase and has started a number of iteration cycles to develop the Architecture. As a packaged application is being considered, the next iteration will include both the Business and Application Architectures.

Stakeholders concerns that should be addressed by these architectures include:

1. What groups of people should be involved in procurement-related business processes?

2. What applications will these groups use once the architecture development is complete?

3. What non-procurement applications will need to be integrated with the new procurement applications?

4. What are the dependences between the non-procurement and the new procurement applications?

Refer to the Scenario

[Note: You may need to refer to the Architectural Artifacts chapter, section 31.6 (located in Part IV) within the reference text in order to answer this question.]

You have been asked to identify the most appropriate catalogs, matrices, and diagrams to support the next iteration of Architecture development.

Based on the TOGAF standard, which of the following is the best answer?

Options:

A.

You would describe the Baseline Business Architecture with a Baseline Business Process catalog, and an Object lifecycle catalog. You would describe the Baseline Application Architecture with an Interface catalog and a Technology Portfolio catalog.

B.

You would describe the Baseline Business Architecture with an Organization/Actor catalog, and a Business Service/Function catalog, and a Data Entity/Business Function matrix. You would describe the Baseline Application Architecture with an Application Portfolio catalog and an Application/Function matrix.

C.

You would describe the Target Business Architecture with a Business Interaction matrix, and a Business Service/Function catalog. You would describe the Target Application Architecture with an Application Communication diagram, an Application/Organization matrix, an Application Interaction matrix and an Interface catalog.

D.

You would describe the Target Business Architecture with a Business Service/Function catalog, an Organization/Actor catalog, and Data Lifecycle diagrams. You would describe the Target Application Architecture with Application Communication diagrams, an Application Interaction matrix, and an Application Portfolio catalog.

Discussion
Addison
Want to tell everybody through this platform that I passed my exam with excellent score. All credit goes to Cramkey Exam Dumps.
Libby Aug 1, 2026
That's good to know. I might check it out for my next IT certification exam. Thanks for the info.
Everleigh
I must say that they are updated regularly to reflect the latest exam content, so you can be sure that you are getting the most accurate information. Plus, they are easy to use and understand, so even new students can benefit from them.
Huxley Aug 20, 2026
That's great to know. So, you think new students should buy these dumps?
Kingsley
Do anyone guide my how these dumps would be helpful for new students like me?
Haris Aug 2, 2026
Absolutely! They are highly recommended for anyone looking to pass their certification exam. The dumps are easy to understand and follow, making it easier for you to study and retain the information.
Conor
I recently used these dumps for my exam and I must say, I was impressed with their authentic material.
Yunus Aug 20, 2026
Exactly…….The information in the dumps is so authentic and up-to-date. Plus, the questions are very similar to what you'll see on the actual exam. I felt confident going into the exam because I had studied using Cramkey Dumps.
Anaya
I found so many of the same questions on the real exam that I had already seen in the Cramkey Dumps. Thank you so much for making exam so easy for me. I passed it successfully!!!
Nina Aug 5, 2026
It's true! I felt so much more confident going into the exam because I had already seen and understood the questions.
Question 37

In which ADM phase is the Implementation and Migration Plan coordinated with other activities in the enterprise?

Options:

A.

Phase A

B.

Phase G

C.

Phase E

D.

Phase H

E.

Phase F

Discussion
Question 38

Which of the following best describes the Standards Information Base?

Options:

A.

A repository area that defines the parameters, structures, and processes to support governance.

B.

A repository area that describes the organization specific architecture framework and methodologies.

C.

A repository area that provides guidelines, templates, and pattern used to create new architectures.

D.

A repository area that lists a set of specifications to which architectures must conform

E.

A repository area that provides a record of the governance activity across the enterprise.

Discussion
Question 39

You are an Enterprise Architect at a food production and distribution company. The primary goal of the company is to maximize profit while satisfying the needs of consumers for its products. Its customers are demanding food that is produced sustainably, safely, and transparently while reducing environmental impact.

The business is highly mechanized, and this mechanization has caused a decrease in the number of workers needed, together with a focus on agricultural engineering to improve the efficiency of its farms, its processing facilities, and the overall enterprise. As part of this, the company has established an Enterprise Architecture (EA) practice based on the TOGAF standard, using it as the method and guiding framework. The Chief Information Officer (CIO) is the sponsor of EA practice. The introduction of EA has enabled the decision-makers to have valuable insights into the different aspects of the business.

Global warming has caused a lot of poor harvests, and the company is producing fewer crops than before. This combined with an increase in costs for energy, feed, fuel, and fertilizer has led to a significant decrease in profits. The rising costs and reduced profits mean that the company is unable to take as much planned action on climate measures as it would like, such as reducing its carbon footprint. In response to the situation, the Chief Executive Officer (CEO) has decided that big changes are needed that will lead both to improved crop production and profitability. They must look to all aspects of the business. This includes looking at the mix of crops to mitigate for the change in climate.

The company will also cease to process its own crops and will sell off its processing facilities. Thus, the target market will change, and the end-products will be different and more varied. A formal request for architecture change has been approved. At this stage, there is no fixed scope, shared vision, or objectives.

Refer to the scenario:

You have been asked to propose the best approach for architecture development to realize the CEO ' s change in direction for the company.

Options:

A.

You propose that the priority is to produce a new Request for Architecture Work leading to the development of a new Architecture Vision. The trade-off method should be applied to identify and select an architecture satisfying the stakeholders. For an efficient change, the EA team should be aligned with the organization ' s planning, budgeting, operational, and change processes.

B.

You propose that this engagement define the baseline Technology Architecture first in order to assess the current infrastructure capacity and capability for the company. Then the focus should be on transition planning and incremental architecture deployment. This will identify requirements to ensure that the projects are sequenced in an optimal fashion so as to realize the change.

C.

You propose that the team uses the architecture definition document and focuses on architecture development starting simultaneously in Phases B, C, and D. This is because the CEO has identified the need to change. This will ensure that the change can be defined in a structured manner and address the requirements needed to realize the change.

D.

You propose that the team focus on architecture definition including the development of business models, with emphasis on defining the change parameters to support this new business strategy that the CEO has identified. Once understood, the team will be in the best position to identify the requirements, drivers, issues, and constraints for the change.

Discussion
Page: 9 / 33
Title
Questions
Posted

OG0-093
PDF

$31.5  $104.99

OG0-093 Testing Engine

$37.5  $124.99

OG0-093 PDF + Testing Engine

$49.5  $164.99