Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

Scrum Updated PSPO-I Exam Questions and Answers by samson

Page: 8 / 12

Scrum PSPO-I Exam Overview :

Exam Name: Professional Scrum Product Owner (PSPO I) Exam
Exam Code: PSPO-I Dumps
Vendor: Scrum Certification: PSPO
Questions: 173 Q&A's Shared By: samson
Question 32

In the middle of the Sprint, the customer decides that there are two new features she wants.

The Product Owner could:

(choose the best two answers)

Options:

A.

Introduce these features at the next Daily Scrum.

B.

Ask the Developers to consider whether they can add these features to thecurrent Sprint without endangering the Sprint Goal.

C.

Add these features to the Product Backlog.

D.

Have the Scrum Master add these features to the current Sprint.

Discussion
Question 33

A Project Manager working with your Scrum Team has raised concerns about progress and money spent. What are the two best responses?

(choose the best two answers)

Options:

A.

Promote transparency by sharing the Product Backlog and ensuring the ProjectManager has access.

B.

Have a discussion with the Project Manager; share the current impediments andforecast for the Sprint.

C.

Show the Earned Value Analysis (EVA) report.

D.

Scrum does not have Project Managers so disregard their concerns.

E.

Share the last stakeholder briefing document prepared by the Product Owner.

Discussion
Question 34

When does a Sprint conclude?

(choose the best answer)

Options:

A.

When all the tasks are completed by the Developers.

B.

When the Sprint Retrospective is complete.

C.

When all Product Backlog items meet their Definition of Done.

D.

When the Product Owner decides enough has been delivered to meet the SprintGoal.

Discussion
Question 35

The IT manager asks a Scrum Team for a status report describing the progress throughout the Sprint. The Scrum Team asks the Scrum Master for advice. The Scrum Master should:

(choose the best answer)

Options:

A.

Tell the Developers to fit the report into the Sprint Backlog.

B.

Ask the Product Owner to send the manager the report.

C.

Create and deliver the report to the manager herself.

D.

Tell the Scrum Team to figure it out themselves.

E.

Talk to the IT manager and explain that progress in Scrum comes from inspecting an Increment at the Sprint Review.

Discussion
Peyton
Hey guys. Guess what? I passed my exam. Thanks a lot Cramkey, your provided information was relevant and reliable.
Coby May 22, 2026
Thanks for sharing your experience. I think I'll give Cramkey a try for my next exam.
Alessia
Amazing Dumps. Found almost all questions in actual exam whih I prepared from these valuable dumps. Recommended!!!!
Belle May 3, 2026
That's impressive. I've been struggling with finding good study material for my certification. Maybe I should give Cramkey Dumps a try.
Ella-Rose
Amazing website with excellent Dumps. I passed my exam and secured excellent marks!!!
Alisha May 10, 2026
Extremely accurate. They constantly update their materials with the latest exam questions and answers, so you can be confident that what you're studying is up-to-date.
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson May 15, 2026
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Page: 8 / 12

PSPO-I
PDF

$36.75  $104.99

PSPO-I Testing Engine

$43.75  $124.99

PSPO-I PDF + Testing Engine

$57.75  $164.99