SAVE International Updated VMA Exam Questions and Answers by isha

Page: 3 / 4

SAVE International VMA Exam Overview :

Exam Name: Value Methodology Associate
Exam Code: VMA Dumps
Vendor: SAVE International Certification: Value Methodology
Questions: 61 Q&A's Shared By: isha
Question 12

The VM is defined by SAVE International as a:

Options:

A.

Structured process

B.

Specialized process

C.

Systematic process

D.

Sequential process

Discussion
Ayesha
They are study materials that are designed to help students prepare for exams and certification tests. They are basically a collection of questions and answers that are likely to appear on the test.
Ayden Jan 8, 2026
That sounds interesting. Why are they useful? Planning this week, hopefully help me. Can you give me PDF if you have ?
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh Jan 13, 2026
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Jan 24, 2026
Thanks for the recommendation! I'll check it out.
Ari
Can anyone explain what are these exam dumps and how are they?
Ocean Jan 4, 2026
They're exam preparation materials that are designed to help you prepare for various certification exams. They provide you with up-to-date and accurate information to help you pass your exams.
Question 13

How many phases are in the VM Job Plan?

Options:

A.

3

B.

6

C.

7

D.

8

Discussion
Question 14

Function E is the:

Options:

A.

Secondary Function

B.

Required Secondary Function

C.

Basic Function

D.

Higher Order Function

Discussion
Question 15

Which is the correct order of steps involved in risk management?

Options:

A.

Risk Management Planning, Risk Analysis, Risk Identification, Risk Response Planning, Risk Monitoring and Control

B.

Risk Identification, Risk Management Planning, Risk Analysis, Risk Response Planning, Risk Monitoring and Control

C.

Risk Management Planning, Risk Identification, Risk Analysis, Risk Response Planning, Risk Monitoring and Control

D.

Risk Management Planning, Risk Identification, Risk Response Planning, Risk Analysis, Risk Monitoring and Control

Discussion