| Exam Name: | PRINCE2 Project Management Practitioner (Version 7) | ||
| Exam Code: | PRINCE2-7-Practitioner Dumps | ||
| Vendor: | PRINCE2 | Certification: | PRINCE2 Certification |
| Questions: | 56 Q&A's | Shared By: | hafsah |
At the start of stage 3, the project board inserts detailed recycling tolerances directly into each work package without the project manager agreeing the delegated targets with the relevant team managers.
Is this an appropriate application of the progress practice, and why?
During stage 1, the City Council purchasing team must prepare the contract that will govern BuildyBrick’s later design and construction work. The project manager agrees with the purchasing team the products, time and cost for this work package.
Which practice is being applied through the ‘controlling a stage’ process?
During stage 4, the business identifies a need for additional funding to extend LouisShopping advertising beyond project closure so that more businesses are attracted to Louistown. The project board must communicate the business need and resulting direction to the project team.
Which role should lead this business-related ongoing direction?
During a periodic evaluation of the security-system work package, the team manager reviews the work package description, team plan, and the related issue, risk, quality, product, and lessons information. Missing electrical cabling means that installation is now forecast to finish one week late, exceeding the work-package time tolerance.
The team manager raises the issue with the project manager and reports the current status in the checkpoint report. Is this an appropriate application of the ‘evaluate a work package’ activity, and why?