Question 12

During stage 2, the Heritage Director, acting as senior user, reviews the design and raises a concern that the previously requested heritage trail has not been addressed.

Is this an appropriate use of the ‘give ongoing direction’ activity, and why?

Options:

A.

Yes, because a project board member may raise concerns and provide ongoing direction within the authority delegated to the board

B.

Yes, because the senior user has an obligation to formally approve key specialist products produced during stages 2 and 3 as a standard action within the ‘give ongoing direction’ activity

C.

No, because the ‘give ongoing direction’ activity is only triggered when the project manager proactively requests a review by the project board, not when individual board members identify concerns independently

D.

No, because the Heritage Director should first seek the agreement of the full project board before raising individual concerns, to ensure a unified project board position is presented to the project manager

Discussion
Question 13

At the end of the initiation stage, the Regeneration Manager submits the project plan and business case for review. The Portfolio Director releases funding for both stages 2 and 3 and instructs the project manager to provide only a progress report at the end of stage 2, without a project board decision before stage 3 begins.

Is this an appropriate application of the ‘manage by stages’ principle, and why?

Options:

A.

Yes, because the project manager is authorized to manage the project on a day-to-day basis within set tolerances throughout each stage, without requiring additional project board decisions

B.

Yes, because the Portfolio Director, as the commissioning authority, has the right to determine the reporting frequency and format that best suit portfolio-level oversight

C.

No, because it is the City Council, rather than the Portfolio Director, that should hold the authority to commit funding across multiple stages of the project

D.

No, because the project board must review the continued viability of the business case and authorize the next stage at each stage boundary, rather than approving multiple stages in advance

Discussion
Aliza
I used these dumps for my recent certification exam and I can say with certainty that they're absolutely valid dumps. The questions were very similar to what came up in the actual exam.
Jakub Aug 16, 2026
That's great to hear. I am going to try them soon.
Joey
I highly recommend Cramkey Dumps to anyone preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Dexter Aug 25, 2026
Agreed. It's definitely worth checking out if you're looking for a comprehensive and reliable study resource.
Hassan
Highly Recommended Dumps… today I passed my exam! Same questions appear. I bought Full Access.
Kasper Aug 4, 2026
Hey wonderful….so same questions , sounds good. Planning to write this week, I will go for full access today.
Reeva
Wow what a success I achieved today. Thank you so much Cramkey for amazing Dumps. All students must try it.
Amari Aug 20, 2026
Wow, that's impressive. I'll definitely keep Cramkey in mind for my next exam.
Question 14

During stage 2, the project board agrees that the underground car park should contain 15 rapid-charging spaces, with a scope tolerance permitting delivery of no fewer than 10 spaces. The project manager includes this tolerance in the relevant work package agreed with the team manager.

Is this an appropriate application of the ‘manage by exception’ principle, and why?

Options:

A.

Yes, because establishing a minimum and a preferred number of charging bays creates a defined scope tolerance that enables the design team to work within an agreed range without needing to escalate every individual design decision

B.

Yes, because specifying a minimum and a preferred number of charging bays constitutes a quality tolerance that the design team must meet within the agreed work package

C.

No, because the precise number of electric charging bays to be included should be fully specified in the product description for the underground car park rather than treated as a tolerance

D.

No, because the project board should approve the precise number of charging spaces rather than delegate a permissible range to the design team

Discussion
Question 15

The Louistown City Council operates a well-established and standardized project management framework that includes a defined procedure for developing business cases. For the LouisShopping Project, a ‘strategic business case’ was included in the project brief submitted to the project board at the conclusion of the ‘starting up a project’ process. The project has now entered the ‘initiating a project’ process, during which the full business case is being built upon the strategic business case, which was itself derived from the Council’s five-year strategic plan for the ‘Louistown is Open for Business’ portfolio.

Does this represent an appropriate application of the ‘business case’ practice, and why?

Options:

A.

Yes, because developing the business case from multiple perspectives – strategic, economic, and commercial – ensures a comprehensive and robust justification for the project investment

B.

Yes, because the project should align its approach to business case development with the City Council’s established procedure, which serves as the equivalent of PRINCE2’s recommended business case lifecycle

C.

No, because the full business case should be developed from an outline business case prepared during the ‘starting up a project’ process, and using a ‘strategic business case’ instead is not compliant with the method

D.

No, because responsibility for developing the full business case for each project in the portfolio lies with the portfolio office, not the project team