Question 8

Company A recently signed a contract with a strategic business partner, Company B, to jointly roll out a new technology Company B is excited about the joint marketing opportunity Company A's component Quality Assurance team has expressed concerns to you the program manager, Ural the product is being rolled out prematurely and has identified potential issues with backend support systems. QA, however, assures you that a manual work around is possible, but not ideal Company B requests an enhancement to the new product. In a meeting with Company B, you determine that additional funding will be required and resources allocated and scheduled

What is your MOST appropriate next step?

Options:

A.

Secure funding from another project that was cancelled

B.

Use an integrated change control process

C.

Use the available management reserve

D.

Advise Company B that funding and resources are not available

Discussion
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Jan 24, 2026
Thanks for the recommendation! I'll check it out.
Lennox
Something Special that they provide a comprehensive overview of the exam content. They cover all the important topics and concepts, so you can be confident that you are well-prepared for the test.
Aiza Jan 25, 2026
That makes sense. What makes Cramkey Dumps different from other study materials?
Sam
Can I get help from these dumps and their support team for preparing my exam?
Audrey Jan 22, 2026
Definitely, you won't regret it. They've helped so many people pass their exams and I'm sure they'll help you too. Good luck with your studies!
Sarah
Yeah, I was so relieved when I saw that the question appeared in the exam were similar to their exam dumps. It made the exam a lot easier and I felt confident going into it.
Aaliyah Jan 20, 2026
Same here. I've heard mixed reviews about using exam dumps, but for us, it definitely paid off.
Pippa
I was so happy to see that almost all the questions on the exam were exactly what I found in their Dumps.
Anastasia Jan 7, 2026
You are right…It was amazing! The Cramkey Dumps were so comprehensive and well-organized, it made studying for the exam a breeze.
Question 9

The program manager plans to address a negative cost variance generating a red flag in the program management status report. What should the program manager do?

Options:

A.

Contact the project sponsors to present the details, impacts, and possible corrective actions regarding the negative cost variance

B.

Gather all the details, analyze impacts, determine corrective actions and present the findings to the governance board for direction

C.

Work with program sponsor to compile impact analysis data to obtain additional funding for the program

D.

Ask the program team to compile all details, analyze impacts, determine corrective actions and present to the governance board for direction

Discussion
Question 10

A program completes all component projects and all identified benefits are being delivered However, the program sponsor is concerned that long-term benefits may not meet organizational performance parameters

To ensure the realization of long-term benefits what should the program manager use?

Options:

A.

Benefits register

B.

Benefits sustainment plan

C.

Benefits management plan

D.

Benefits transition plan

Discussion
Question 11

A program delivers incremental benefits but is far from closure. The company completes an acquisition and defines new strategic objectives.

What should the program manager do next?

Options:

A.

Evaluate the impact of the new strategic objectives through a change request

B.

Integrate the new acquisition into the program to include the new strategic objectives

C.

Assess the impact of the new acquisition on the contract management plan

D.

Review the benefits management plan to assess the continued validity of the program

Discussion