Question 20

In which of the following ways Open PS allows you to exchange data directly with MS project?

There are 3 correct answers to this question.

Response:

Options:

A.

Create a project in MS project from an SAP PS project

B.

Transfer a project from MS project to SAP PS

C.

Download MS project and Upload to SAP PS

D.

Reconcile data from a project in Microsoft Project with a project in SAP PS

Discussion
Laila
They're such a great resource for anyone who wants to improve their exam results. I used these dumps and passed my exam!! Happy customer, always prefer. Yes, same questions as above I know you guys are perfect.
Keira Aug 12, 2024
100% right….And they're so affordable too. It's amazing how much value you get for the price.
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony Sep 10, 2024
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Melody
My experience with Cramkey was great! I was surprised to see that many of the questions in my exam appeared in the Cramkey dumps.
Colby Aug 17, 2024
Yes, In fact, I got a score of above 85%. And I attribute a lot of my success to Cramkey's dumps.
Everleigh
I must say that they are updated regularly to reflect the latest exam content, so you can be sure that you are getting the most accurate information. Plus, they are easy to use and understand, so even new students can benefit from them.
Huxley Aug 26, 2024
That's great to know. So, you think new students should buy these dumps?
Erik
Hey, I have passed my exam using Cramkey Dumps?
Freyja Oct 17, 2024
Really, what are they? All come in your pool? Please give me more details, I am going to have access their subscription. Please brother, give me more details.
Question 21

Which of the following prerequisites need to be met in order to analyze the capacity requirements of an activity?

There are 3 correct answers to this question.

Response:

Options:

A.

Scheduling must have been carried

B.

A distribution key must be maintained in the work center

C.

A work center must be maintained in the activity

D.

The capacity requirements indicator must not be set in the network header

Discussion
Question 22

How are various stock types managed for each material component?

Please choose the correct answer.

Response:

Options:

A.

Account assignment category

B.

Material group

C.

Item Category

D.

Billing type

Discussion
Question 23

With reference to material requirements in Project System (PS-MAT), which of the following statements are true?

Please choose the correct answer.

Response:

Options:

A.

9999 components may be created per network.

B.

Project System supports consignment stock.

C.

Component scrap is considered during BOM explosion.

Discussion