Question 20

How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 Correct answers to this question.

Options:

A.

Increase the capacity supply in a time-phased interval.

B.

Determine a time period with available capacity on the planning board.

C.

Execute an infinite production planning run for the critical resources.

D.

Reduce the planning Window.

E.

Form optimum sequence to reduce setup times.

Discussion
Ava-Rose
Yes! Cramkey Dumps are amazing I passed my exam…Same these questions were in exam asked.
Ismail Sep 18, 2024
Wow, that sounds really helpful. Thanks, I would definitely consider these dumps for my certification exam.
Mylo
Excellent dumps with authentic information… I passed my exam with brilliant score.
Dominik Aug 29, 2024
That's amazing! I've been looking for good study material that will help me prepare for my upcoming certification exam. Now, I will try it.
River
Hey, I used Cramkey Dumps to prepare for my recent exam and I passed it.
Lewis Sep 11, 2024
Yeah, I used these dumps too. And I have to say, I was really impressed with the results.
Vienna
I highly recommend them. They are offering exact questions that we need to prepare our exam.
Jensen Oct 9, 2024
That's great. I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Teddie
yes, I passed my exam with wonderful score, Accurate and valid dumps.
Isla-Rose Aug 18, 2024
Absolutely! The questions in the dumps were almost identical to the ones that appeared in the actual exam. I was able to answer almost all of them correctly.
Question 21

Which information is required when you create a product master in SAP S/4HANA?

Note: There are 2 correct answers to this question.

Options:

A.

Product type

B.

Selection screen for views

C.

Selection screen for plants

D.

Base unit of measure

Discussion
Question 22

where does the system check master data selection settings during the creation of planned orders and production orders?

Note: There are 3 Correct answers to this question.

Options:

A.

in the bill of material (BOM)

B.

in the work centers

C.

in the MRP controller

D.

In the routing

E.

in the production version

Discussion
Question 23

What is the purpose of a reporting point confirmation in repetitive manufacturing?

Note: There are 2 Correct answers to this question?

Options:

A.

To determine the work in progress along the production line

B.

To provide timely updates of inventory management for the staged components

C.

To reduce the total production lead time for a long production line

D.

To stage different components for a production line simultaneously

Discussion