PRINCE2 Updated PRINCE2-Agile-Foundation Exam Questions and Answers by kyran

Page: 9 / 11

PRINCE2 PRINCE2-Agile-Foundation Exam Overview :

Exam Name: PRINCE2 Agile Foundation (Version 2) Exam
Exam Code: PRINCE2-Agile-Foundation Dumps
Vendor: PRINCE2 Certification: PRINCE2 Agile
Questions: 162 Q&A's Shared By: kyran
Question 36

Which statement about the ‘be on time and hit deadlines’ target is CORRECT?

Options:

A.

It allows change to be handled dynamically

B.

It is achieved by keeping the delivery teams stable

C.

It helps with planning dependencies within a project

D.

It ensures that the level of quality is protected

Discussion
Question 37

Which tool is used to assess risks associated with Agile adoption?

Options:

A.

Enterprise agility assessment

B.

Project dashboard

C.

Agilometer assessment

D.

Cumulative risk burn-down chart

Discussion
Kylo
What makes Cramkey Dumps so reliable? Please guide.
Sami Jul 28, 2026
Well, for starters, they have a team of experts who are constantly updating their material to reflect the latest changes in the industry. Plus, they have a huge database of questions and answers, which makes it easy to study and prepare for the exam.
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka Jul 28, 2026
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Ace
No problem! I highly recommend Cramkey Dumps to anyone looking to pass their certification exams. They will help you feel confident and prepared on exam day. Good luck!
Harris Jul 25, 2026
That sounds amazing. I'll definitely check them out. Thanks for the recommendation!
Walter
Yayyy!!! I passed my exam with the help of Cramkey Dumps. Highly appreciated!!!!
Angus Jul 18, 2026
YES….. I saw the same questions in the exam.
Question 38

During which process should release planning be done for the FIRST time?

Options:

A.

Initiating a project

B.

Managing a stage boundary

C.

Managing product delivery

D.

Controlling a stage

Discussion
Question 39

Which TWO project board responsibilities are specifically assigned to the senior user?

1) Demonstrating the achievement of benefits.

2) Specifying the needs of those impacted by the outputs.

3) Balancing business, user and supplier demands.

4) Ensuring that the project delivers value for money.

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Discussion