Which of the following should be considered the biggest risk to the schedule when trying to implement formal scripted test cases early in the SDLC for a system with a
large GUI front end? [2]
You are a Test Manager at a company that develops mobile phone applications. Based on historical data in your company, you have calculated the following average metrics for system testing:
• for each 100 LOC (Lines Of Code). 4 test cases are executed
• each test case takes on average 15 minutes to execute and check
• for each 1000 LOC, 5 defects are found
You have used this information to create an estimate for the system testing of a new mobile phone application being developed to submit gas and electricity readings.
The application delivered for system testing has 50.000 lines of code. At the end of system testing, 250 defects are discovered.
Assume that:
• the system test of the new mobile phone application will require the same amount of effort as previous applications
• defect density = number of defects/1000 LOC
• no new tools or processes have been introduced to the test team
Based only on the given information, which one of the following statements is true about this new mobile phone application?
SELECT ONE OPTION
Your company specialises in the manufacture of luxury garden furniture to the UK market and it is starting a project that will deliver a major update to its payment processing component, addressing improvements to functional suitability and performance efficiency.
A decision has been made to transfer responsibility for functional system test procedure creation and execution to a software house, located offshore. System test analysis and design will be performed onshore, at the company's UK headquarters. As the senior test manager for your company, you want to employ another experienced test manager to oversee the daily operations of the software house to ensure that their work meets required quality standards and adheres to the agreed organisational test strategy and project test plan.
Which option presents the skills that are of MOST relevance for the new test manager role?
You feel that your team has become lazy when applying good software testing techniques You have given each of them a challenge to take a different business rule and build a full decision tableand then collapse that table You will then assess the results For this assessment, what competencies are you validating?