Question 60

In the Work Breakdown Structure, larger tasks are called…

Options:

A.

Sub-projects

B.

Milestones

C.

Blocks

D.

Phases

Discussion
Question 61

It’s come to your attention that some team members feel that Carlos is a negative influence on the team. You can certainly understand why – he believes that everything is doomed. What should you do?

Options:

A.

Remove Carlos from the team.

B.

Use Carlos as an asset, particularly during risk identification

C.

Ignore him and hope it goes away

D.

Escalate the issue with the higher authorities]

Discussion
Lennox
Something Special that they provide a comprehensive overview of the exam content. They cover all the important topics and concepts, so you can be confident that you are well-prepared for the test.
Aiza Oct 25, 2024
That makes sense. What makes Cramkey Dumps different from other study materials?
Walter
Yayyy!!! I passed my exam with the help of Cramkey Dumps. Highly appreciated!!!!
Angus Nov 4, 2024
YES….. I saw the same questions in the exam.
Ivan
I tried these dumps for my recent certification exam and I found it pretty helpful.
Elis Sep 17, 2024
Agree!!! The questions in the dumps were quite similar to what came up in the actual exam. It gave me a good idea of the types of questions to expect and helped me revise efficiently.
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony Sep 10, 2024
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Question 62

The person who typically initiates the project and provides the authority within the organization is called…

Options:

A.

The project manager

B.

The sponsor

C.

The subject matter expert

D.

The Subordinate

Discussion
Question 63

Which of the following skills might a project manager need?

Options:

A.

Writing

B.

Speaking

C.

Persuading

D.

All of the above

Discussion
Page: 15 / 16

PPM-001
PDF

$42  $104.99

PPM-001 Testing Engine

$50  $124.99

PPM-001 PDF + Testing Engine

$66  $164.99