Exin CITM Exam Overview :

Exam Name: EXIN EPI Certified Information Technology Manager
Exam Code: CITM Dumps
Vendor: Exin Certification: EPI IT Management
Questions: 50 Q&A's Shared By: frazer
Question 12

Senior management suspects possible threats in the IT organization and demands a high-level assessment which will list risks identified in order of priority for treatment. Which type of analysis should be conducted?

Options:

A.

Quantitative analysis

B.

Semi-quantitative analysis

C.

Ad hoc analysis

D.

Qualitative analysis

Discussion
Esmae
I highly recommend Cramkey Dumps to anyone preparing for the certification exam.
Mollie Nov 15, 2025
Absolutely. They really make it easier to study and retain all the important information. I'm so glad I found Cramkey Dumps.
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Nov 7, 2025
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka Nov 19, 2025
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Sarah
Yeah, I was so relieved when I saw that the question appeared in the exam were similar to their exam dumps. It made the exam a lot easier and I felt confident going into it.
Aaliyah Nov 27, 2025
Same here. I've heard mixed reviews about using exam dumps, but for us, it definitely paid off.
Question 13

When selecting a new vendor, continuity needs to be guaranteed as much as possible. At a minimum, which criteria are considered?

Options:

A.

Scope, maintenance, and price

B.

Terms and conditions, maintenance, and terms of engagement

C.

Price, training, and support

D.

Head count, support, and financial stability

Discussion
Question 14

Activities in a project are discussed in a Work Breakdown Structure (WBS) session during the planning phase. Team members inform the project manager that whilst estimating the duration for activities, a lot of data exist about the effort required for each of them. Which estimation technique is best considered?

Options:

A.

Top-down

B.

Three-point

C.

Comparative

D.

Bottom-up

Discussion
Question 15

The new system (application) is ready for adoption (implementation). The customer is concerned that an instant change-over from the current system to the new system will create a large impact on the user base. You are requested to propose an approach for adoption. Which of the items listed below is recommended?

Options:

A.

Big bang

B.

Parallel

C.

Coordinated

D.

Phased

Discussion