Exin CITM Exam Overview :

Exam Name: EXIN EPI Certified Information Technology Manager
Exam Code: CITM Dumps
Vendor: Exin Certification: EPI IT Management
Questions: 50 Q&A's Shared By: allegra
Question 8

Whilst creating the budget for the project, stakeholders demand that the project manager submits a budget proposal as accurate as possible, supported by a Work/Product Breakdown Structure (WBS/PBS). What is the preferred budget estimation?

Options:

A.

Bottom-up estimate

B.

Rough Order of Magnitude (ROM)

C.

Analogous estimate

D.

Budget estimate

Discussion
Nadia
Why these dumps are important? Can I pass my exam without these dumps?
Julian Aug 10, 2026
The questions in the Cramkey dumps are explained in detail and there are also study notes and reference materials provided. This made it easier for me to understand the concepts and retain the information better.
Josie
I just passed my certification exam using their dumps and I must say, I was thoroughly impressed.
Fatimah Aug 26, 2026
You’re right. The dumps were authentic and covered all the important topics. I felt confident going into the exam and it paid off.
Miley
Hey, I tried Cramkey Dumps for my IT certification exam. They are really awesome and helped me pass my exam with wonderful score.
Megan Aug 15, 2026
That’s great!!! I’ll definitely give it a try. Thanks!!!
Billy
It was like deja vu! I was confident going into the exam because I had already seen those questions before.
Vincent Aug 25, 2026
Definitely. And the best part is, I passed! I feel like all that hard work and preparation paid off. Cramkey is the best resource for all students!!!
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka Aug 23, 2026
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Question 9

During the system (application) development project, the customer wants to know how software will be maintained to assure that future functional requirements are incorporated. What type of system maintenance is the customer looking for?

Options:

A.

Preventive maintenance

B.

Perfective maintenance

C.

Corrective maintenance

D.

Adaptive maintenance

Discussion
Question 10

Due to technical and operational constraints, the preferred control to lower the risks identified is to outsource part of IT operations to an external vendor. What type of risk treatment is applied here?

Options:

A.

Sharing

B.

Retention

C.

Transferred

D.

Modification

Discussion
Question 11

Before the marketing department will decide on a new advertising campaign, it wants to be able to gain more insights into the customer, being able to predict the products customers will purchase in the near future. What is a ‘must-have’ criterion in terms of the technology the marketing department is interested in?

Options:

A.

Records Management System (RMS)

B.

Advanced analytics

C.

Ad hoc analysis

D.

Business Intelligence (BI)

Discussion